4220 S HOBART BLVD 90062
Certificate Information: 4220 S HOBART BLVD 90062
- Application / Permit
- 20014-20000-00751
- Plan Check / Job No.
- B20VN02818
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 20' X 11' 6" TO (E) DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 7/1/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/19/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 2/19/2020 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 2/24/2020 | APPLICANT |
| Plan Check Approved | 3/19/2020 | GURUNATH NESARAJAH |
| Issued | 7/1/2021 | APPLICANT |
| CofO in Progress | 2/28/2022 | HORACE FULTZ |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
| CofO Issued | 3/5/2022 | DEROLD HAUFF |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2020 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 3/10/2020 | TORI CHEN |
| Construction within easement | Cleared | 3/10/2020 | TORI CHEN |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 3/10/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/10/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Ivy Green Construction; Lic. No.: 1014647-B | 16200 VENTURA BLVD STE 317 ENCINO, CA 91436 |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 13719 OXNARD ST 101 VAN NUYS, CA 91401 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/19/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/21/2021 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 7/28/2021 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/15/2021 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 9/15/2021 | Not Ready for Inspection | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 9/15/2021 | Not Ready for Inspection | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 9/17/2021 | No Access for Inspection | HORACE FULTZ |
| BUILDING-Rough-Frame | 9/22/2021 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 9/22/2021 | Not Ready for Inspection | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 9/22/2021 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/30/2021 | No Access for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | No Access for Inspection | SABAS ALONSO |
| Green Building Rough | 9/30/2021 | No Access for Inspection | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 9/30/2021 | No Access for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/6/2021 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Approved | SABAS ALONSO |
| Green Building Rough | 10/6/2021 | Approved | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 10/6/2021 | Approved | SABAS ALONSO |
| Insulation | 10/14/2021 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 10/14/2021 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 10/20/2021 | Approved | SABAS ALONSO |
| Drywall Nailing | 10/25/2021 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 1/14/2022 | SGSOV Not Ready | SABAS ALONSO |
| ELECTRICAL-Final | 1/21/2022 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 1/21/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 1/21/2022 | Not Ready for Inspection | SABAS ALONSO |
| Final | 1/27/2022 | Not Ready for Inspection | HORACE FULTZ |
| Green Building Final | 1/27/2022 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 1/27/2022 | SGSOV Not Ready | HORACE FULTZ |
| Smoke Detectors | 1/27/2022 | Approved | HORACE FULTZ |
| Special/Order Compliance | 1/31/2022 | Corrections Issued | HORACE FULTZ |
| Final | 2/9/2022 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/9/2022 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 2/15/2022 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/16/2022 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 2/16/2022 | Approved | SABAS ALONSO |
| Final | 2/24/2022 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/24/2022 | SGSOV Approved | SABAS ALONSO |
| Final | 2/28/2022 | OK to Issue CofO | SABAS ALONSO |