16650 W BERMUDA ST 91344
Certificate Information: 16650 W BERMUDA ST 91344
- Application / Permit
- 20014-20000-00747
- Plan Check / Job No.
- B20VN02803
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 5'-0" X 16'-2" ADDITION TO CONVERT THE (E) DETACHED GARAGE INTO (N) ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP
- Permit Issued
- Issued on 6/29/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/19/2020 | ARTIN ZARUKIAN |
| Corrections Issued | 2/19/2020 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 3/11/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 4/8/2020 | RAPHAEL ROSAS |
| Issued | 6/29/2020 | LADBS |
| CofO in Progress | 5/18/2022 | MICHAEL TEMPLE |
| Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
| CofO Issued | 8/30/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2020 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2020 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 3/9/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 3/9/2020 | MARKOS PEREZ-BRAN |
| Construction near power lines | Cleared | 3/11/2020 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/5/2020 | Partial Approval | MARK JOHNSON |
| Sewer | 10/5/2020 | Not Ready for Inspection | MARK JOHNSON |
| Footing/Foundation/Slab | 11/2/2020 | Approved | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 5/26/2021 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 5/26/2021 | Corrections Issued | MARK JOHNSON |
| Green Building Rough | 5/26/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 5/26/2021 | Approved | MARK JOHNSON |
| Wood Frame | 5/26/2021 | Not Ready for Inspection | MARK JOHNSON |
| BUILDING-Rough-Frame | 7/1/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 7/1/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 7/1/2021 | Approved | MARK JOHNSON |
| HVAC-Rough | 7/1/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 7/1/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 7/26/2021 | Not Ready for Inspection | MARK JOHNSON |
| Insulation | 7/29/2021 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 7/29/2021 | Approved | WILLIAM WREN |
| Drywall Nailing | 9/20/2021 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/27/2021 | Approved | ADAM ESCOTO |
| Gas Test | 10/27/2021 | Approved | MARK JOHNSON |
| Sewer | 1/19/2022 | Approved | JESUS RODRIGUEZ |
| Gas Test | 3/1/2022 | Approved | DEANDRE HOFFMAN |
| Final | 3/11/2022 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Final | 3/11/2022 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 3/11/2022 | SGSOV Approved | MICHAEL TEMPLE |
| Smoke Detectors | 3/11/2022 | Approved | MICHAEL TEMPLE |
| Final | 5/17/2022 | OK to Issue CofO | MICHAEL TEMPLE |