16650 W BERMUDA ST 91344

Certificate Information: 16650 W BERMUDA ST 91344

Application / Permit
20014-20000-00747
Plan Check / Job No.
B20VN02803
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
5'-0" X 16'-2" ADDITION TO CONVERT THE (E) DETACHED GARAGE INTO (N) ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP
Permit Issued
Issued on 6/29/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/19/2020 APPLICANT
Assigned to Plan Check Engineer 2/19/2020 ARTIN ZARUKIAN
Corrections Issued 2/19/2020 ARTIN ZARUKIAN
Applicant returned to address corrections 3/11/2020 JEROME MAGAT PALMA
Plan Check Approved 4/8/2020 RAPHAEL ROSAS
Issued 6/29/2020 LADBS
CofO in Progress 5/18/2022 MICHAEL TEMPLE
Permit Finaled 8/30/2022 DANIEL ORRANTE
Permit Finaled 8/30/2022 DANIEL ORRANTE
CofO Issued 8/30/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/9/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 3/9/2020 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 3/9/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 3/9/2020 MARKOS PEREZ-BRAN
Construction near power lines Cleared 3/11/2020 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/5/2020 Partial Approval MARK JOHNSON
Sewer 10/5/2020 Not Ready for Inspection MARK JOHNSON
Footing/Foundation/Slab 11/2/2020 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 5/26/2021 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 5/26/2021 Corrections Issued MARK JOHNSON
Green Building Rough 5/26/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 5/26/2021 Approved MARK JOHNSON
Wood Frame 5/26/2021 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 7/1/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 7/1/2021 Approved MARK JOHNSON
Green Building Rough 7/1/2021 Approved MARK JOHNSON
HVAC-Rough 7/1/2021 Approved MARK JOHNSON
PLUMBING-Rough 7/1/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 7/26/2021 Not Ready for Inspection MARK JOHNSON
Insulation 7/29/2021 Approved WILLIAM WREN
Interior/Exterior Lathing 7/29/2021 Approved WILLIAM WREN
Drywall Nailing 9/20/2021 Approved LILIANA PORTILLO
Interior/Exterior Lathing 9/27/2021 Approved ADAM ESCOTO
Gas Test 10/27/2021 Approved MARK JOHNSON
Sewer 1/19/2022 Approved JESUS RODRIGUEZ
Gas Test 3/1/2022 Approved DEANDRE HOFFMAN
Final 3/11/2022 Corrections Issued MICHAEL TEMPLE
Green Building Final 3/11/2022 Approved MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 3/11/2022 SGSOV Approved MICHAEL TEMPLE
Smoke Detectors 3/11/2022 Approved MICHAEL TEMPLE
Final 5/17/2022 OK to Issue CofO MICHAEL TEMPLE