7714 N WISH AVE 91406
Certificate Information: 7714 N WISH AVE 91406
- Application / Permit
- 20014-20000-00745
- Plan Check / Job No.
- B20VN02798
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE 18'-1" X 3'-9" PORTION OF DETACHED GARAGE, ADD IREGULAR SHAPED 25'-11" X 37'-1" AND CONVERT TO ACCESSORY DWELLING UNIT. ALL WORKS ARE PER WFPP.
- Permit Issued
- Issued on 2/26/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/9/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/19/2020 | ARTIN ZARUKIAN |
| Corrections Issued | 2/19/2020 | ARTIN ZARUKIAN |
| Plan Check Approved | 2/26/2020 | ALDOUS CHIC |
| Issued | 2/26/2020 | LADBS |
| CofO in Progress | 7/9/2020 | DANIEL ORRANTE |
| Permit Finaled | 7/9/2020 | DANIEL ORRANTE |
| CofO Issued | 7/9/2020 | DANIEL ORRANTE |
| Permit Finaled | 7/9/2020 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/19/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 2/19/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 2/25/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/25/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/10/2020 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 3/10/2020 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 3/19/2020 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2020 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2020 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Gas Test | 3/28/2020 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 3/28/2020 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 3/28/2020 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 4/2/2020 | Partial Approval | MARK JOHNSON |
| ELECTRICAL-Rough | 4/2/2020 | Approved | MARK JOHNSON |
| Green Building Rough | 4/2/2020 | Approved | MARK JOHNSON |
| Shower Pan | 4/2/2020 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 4/7/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 4/9/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/9/2020 | Approved | MATTHEW NELSON |
| Service/Power Release | 4/30/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Gas Test | 5/7/2020 | Partial Approval | MISAEL ESPARZA |
| Sewer | 5/7/2020 | Approved | MISAEL ESPARZA |
| Service/Power Release | 5/18/2020 | Not Ready for Inspection | TROY SANDERS |
| Drywall Nailing | 5/27/2020 | Approved | MISAEL ESPARZA |
| Final | 5/27/2020 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 5/27/2020 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/27/2020 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 5/27/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 5/27/2020 | Approved | MISAEL ESPARZA |
| Service/Power Release | 6/10/2020 | Approved | JEFFREY PARD |
| Final | 6/12/2020 | OK to Issue CofO | JOHN HAYES |