7714 N WISH AVE 91406

Certificate Information: 7714 N WISH AVE 91406

Application / Permit
20014-20000-00745
Plan Check / Job No.
B20VN02798
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 18'-1" X 3'-9" PORTION OF DETACHED GARAGE, ADD IREGULAR SHAPED 25'-11" X 37'-1" AND CONVERT TO ACCESSORY DWELLING UNIT. ALL WORKS ARE PER WFPP.
Permit Issued
Issued on 2/26/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/9/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/19/2020 APPLICANT
Assigned to Plan Check Engineer 2/19/2020 ARTIN ZARUKIAN
Corrections Issued 2/19/2020 ARTIN ZARUKIAN
Plan Check Approved 2/26/2020 ALDOUS CHIC
Issued 2/26/2020 LADBS
CofO in Progress 7/9/2020 DANIEL ORRANTE
Permit Finaled 7/9/2020 DANIEL ORRANTE
CofO Issued 7/9/2020 DANIEL ORRANTE
Permit Finaled 7/9/2020 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/19/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 2/19/2020 GUILLERMO PETRA
Sewer availability Cleared 2/19/2020 GUILLERMO PETRA
Low Impact Development Cleared 2/25/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/25/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/10/2020 Partial Approval JACK KARGODORIAN
Underground Mechanical 3/10/2020 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 3/19/2020 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 3/25/2020 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/26/2020 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/28/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Gas Test 3/28/2020 Approved KATHRYN BUTTERWORTH
HVAC-Rough 3/28/2020 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 3/28/2020 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 4/2/2020 Partial Approval MARK JOHNSON
ELECTRICAL-Rough 4/2/2020 Approved MARK JOHNSON
Green Building Rough 4/2/2020 Approved MARK JOHNSON
Shower Pan 4/2/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 4/7/2020 Approved MATTHEW NELSON
Drywall Nailing 4/9/2020 Not Ready for Inspection MATTHEW NELSON
Interior/Exterior Lathing 4/9/2020 Approved MATTHEW NELSON
Service/Power Release 4/30/2020 Not Ready for Inspection JENNIFER RABUCHIN
Gas Test 5/7/2020 Partial Approval MISAEL ESPARZA
Sewer 5/7/2020 Approved MISAEL ESPARZA
Service/Power Release 5/18/2020 Not Ready for Inspection TROY SANDERS
Drywall Nailing 5/27/2020 Approved MISAEL ESPARZA
Final 5/27/2020 Corrections Issued MISAEL ESPARZA
Green Building Final 5/27/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/27/2020 SGSOV Approved MISAEL ESPARZA
Service/Power Release 5/27/2020 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 5/27/2020 Approved MISAEL ESPARZA
Service/Power Release 6/10/2020 Approved JEFFREY PARD
Final 6/12/2020 OK to Issue CofO JOHN HAYES