12543 N NEDRA DR 91344
Certificate Information: 12543 N NEDRA DR 91344
- Application / Permit
- 20014-20000-00738
- Plan Check / Job No.
- B20VN02771
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 14'-5" X 30' 2ND-FLOOR ADDITION TO (E) 2-STORY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 1/4/2022
- Issuing Office
- Current Status
- CofO Issued on 3/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | SERGIO MUNIZ |
| Corrections Issued | 3/19/2020 | SERGIO MUNIZ |
| Quality Review Completed | 4/6/2020 | OMID HEDAYAT |
| Green Plans Picked Up | 4/8/2020 | APPLICANT |
| Applicant returned to address corrections | 10/14/2021 | SERGIO MUNIZ |
| Plan Check Approved | 11/8/2021 | SERGIO MUNIZ |
| Building Plans Picked Up | 11/9/2021 | APPLICANT |
| Issued | 1/4/2022 | APPLICANT |
| CofO in Progress | 2/24/2023 | JAVIER RAMOS JR |
| CofO Issued | 3/7/2023 | MICHAEL SMITH |
| Permit Finaled | 3/7/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/12/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/12/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2021 | GABRIEL ROBLES |
| ZA Case | Cleared | 8/19/2021 | MAXFIELD VERMY |
| Grading Pre-Inspection | Cleared | 8/30/2021 | VASIL MIHALEV |
| Green Code | Cleared | 10/14/2021 | AARON COSTA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/21/2022 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 1/24/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 1/28/2022 | Approved | RAUL OLAGI |
| Deputy Wood Construction | 2/10/2022 | Conditional Approval | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2022 | Partial Approval | JESUS RODRIGUEZ |
| Wood Frame | 3/10/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 4/1/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 7/21/2022 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/21/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2022 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 7/21/2022 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/27/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/27/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 7/27/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 7/27/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 7/27/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/10/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Drywall Nailing | 8/10/2022 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 8/10/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/18/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 10/18/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 11/28/2022 | Approved | JAVIER RAMOS JR |
| Final | 11/28/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 11/28/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 11/28/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 11/28/2022 | Approved | JAVIER RAMOS JR |
| Final | 2/24/2023 | OK to Issue CofO | JAVIER RAMOS JR |