7500 N PASO ROBLES AVE 91406

Certificate Information: 7500 N PASO ROBLES AVE 91406

Application / Permit
20014-20000-00734
Plan Check / Job No.
B20VN02766
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 7'-4" x 13'-1" PORTION OF THE (E) GARAGE INTO BATHROOM AND LAUNDRY ROOM. ADD 7'-0" x 13'-1" TO EXTEND (E)GARAGE TO INCREASE THE DEPTH. 7'-0" x 8'-3" IRREGULAR SHAPED ADDITION FOR (N)COVERED ENTRY ATTACHED TO (E)SINGLE FAMILY DWELLING.
Permit Issued
Issued on 3/2/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2020 APPLICANT
Assigned to Plan Check Engineer 2/18/2020 SARKIS HARABEDIAN
Corrections Issued 2/18/2020 SARKIS HARABEDIAN
Plan Check Approved 3/2/2020 JEROME MAGAT PALMA
Issued 3/2/2020 LADBS
CofO in Progress 9/24/2020 MARK JOHNSON
CofO Issued 11/21/2020 MICHAEL SMITH
Permit Finaled 11/21/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/18/2020 JOHN LIN
Roof/Waste drainage to street Cleared 2/18/2020 JOHN LIN
Public Works-Highway Ded. Cleared 2/18/2020 JOHN LIN
Public Works-Open Permits Cleared 2/18/2020 JOHN LIN
Public Works-Sewers Cleared 2/18/2020 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/21/2020 Approved MATTHEW NELSON
Footing/Foundation/Slab 5/26/2020 Approved ROBERT MINASSIANS
Pre-Inspection 5/29/2020 Not Ready for Inspection DANIEL ORRANTE
BUILDING-Rough-Frame 7/17/2020 Not Ready for Inspection DANIEL DREW
ELECTRICAL-Rough 7/17/2020 Not Ready for Inspection DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 7/17/2020 Approved DANIEL DREW
Green Building Rough 7/17/2020 Approved DANIEL DREW
PLUMBING-Rough 7/22/2020 Approved DANIEL DREW
BUILDING-Rough-Frame 7/24/2020 Approved DANIEL DREW
ELECTRICAL-Rough 7/24/2020 Approved DANIEL DREW
Insulation 7/24/2020 Approved DANIEL DREW
Drywall Nailing 7/31/2020 Approved DANIEL DREW
Shower Pan 8/11/2020 Approved MICHEL ABAJAN
Final 9/14/2020 Corrections Issued BRENDAN LOONEY
Green Building Final 9/14/2020 Approved BRENDAN LOONEY
Smoke Detectors 9/14/2020 Approved BRENDAN LOONEY
ELECTRICAL-Final 9/23/2020 Approved MARK JOHNSON
Final 9/23/2020 OK to Issue CofO MARK JOHNSON
HVAC-Final 9/23/2020 Approved MARK JOHNSON
PLUMBING-Final 9/23/2020 Approved MARK JOHNSON