7543 S TRASK AVE 90293
Certificate Information: 7543 S TRASK AVE 90293
- Application / Permit
- 20014-20000-00728
- Plan Check / Job No.
- B20VN02749
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE 231SF STORAGE ADDITION WITH DECK ABOVE, AND PROPOSE (419SF) HABITABLE BASEMENT WITH STAIR ACCESS THROUGH (E) SFD.
- Permit Issued
- Issued on 12/9/2021
- Issuing Office
- Current Status
- CofO Issued on 2/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | DAWN MC NULTY |
| Green Plans Picked Up | 3/6/2020 | APPLICANT |
| Corrections Issued | 3/10/2020 | DAWN MC NULTY |
| Quality Review Completed | 3/17/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/18/2020 | APPLICANT |
| Applicant returned to address corrections | 9/25/2020 | DAWN MC NULTY |
| Applicant returned to address corrections | 12/3/2020 | DAWN MC NULTY |
| Plan Check Approved | 10/13/2021 | DAWN MC NULTY |
| Issued | 12/9/2021 | APPLICANT |
| CofO in Progress | 2/27/2024 | BOBBY KEY |
| Permit Finaled | 2/29/2024 | DANIEL ORRANTE |
| CofO Issued | 2/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/18/2020 | GABRIEL ROBLES |
| CPC | Cleared | 4/15/2020 | PABLO ESTRADA |
| CPC | Cleared | 4/15/2020 | PABLO ESTRADA |
| CPC | Cleared | 4/15/2020 | PABLO ESTRADA |
| CPC | Cleared | 4/15/2020 | PABLO ESTRADA |
| CPC | Cleared | 4/15/2020 | PABLO ESTRADA |
| CPC | Cleared | 4/15/2020 | PABLO ESTRADA |
| ZA Case | Cleared | 4/15/2020 | PABLO ESTRADA |
| Work Adjacent to Public Way | Cleared | 7/7/2020 | ANTHONY MAINEZ |
| Green Code | Cleared | 8/18/2020 | MICHAEL AYERS |
| Low Impact Development | Cleared | 9/15/2020 | ORVAL HERNANDEZ-MARCI |
| Miscellaneous | Cleared | 12/3/2020 | DAWN MC NULTY |
| Encroachment in public way | Cleared | 12/28/2020 | CATHERINE ADROVER |
| Coastal Zone | Cleared | 2/4/2021 | MAXFIELD VERMY |
| Roof/Waste drainage to street | Cleared | 6/16/2021 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 7/14/2021 | PATRICK MISCHLICH |
| GPI Written Notices | Cleared | 9/13/2021 | DAWN MC NULTY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Engineer | Haro,, Ruben; Lic. No.: GE2990 | 555 N LANTANA ST STE 492 CAMARILLO, CA 93010 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 4/15/2022 | Not Ready for Inspection | BOBBY KEY |
| Deputy Reinf. Concrete | 4/21/2022 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 5/16/2022 | Partial Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 5/18/2022 | Conditional Approval | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 6/8/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 6/8/2022 | Partial Approval | BOBBY KEY |
| Deputy Drilled-In Anchors | 6/15/2022 | Conditional Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 6/17/2022 | Corrections Issued | PATRICK QUALEY |
| Footing/Foundation/Slab | 6/17/2022 | Partial Approval | PATRICK QUALEY |
| Excavation/Setback/Form/Re-Bar | 6/24/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 6/24/2022 | Approved | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 7/6/2022 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 7/8/2022 | Approved | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 7/13/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 7/27/2022 | Conditional Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 7/28/2022 | Not Ready for Inspection | BOBBY KEY |
| Wood Frame | 10/14/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2022 | Partial Approval | BOBBY KEY |
| Insulation | 11/16/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 11/16/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 12/12/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 12/12/2022 | Approved | BOBBY KEY |
| Green Building Rough | 12/12/2022 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 12/12/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 12/30/2022 | Partial Approval | BOBBY KEY |
| Green Building Rough | 12/30/2022 | Partial Approval | BOBBY KEY |
| Insulation | 12/30/2022 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 12/30/2022 | Not Ready for Inspection | BOBBY KEY |
| Drywall Nailing | 2/1/2023 | Partial Approval | BOBBY KEY |
| Green Building Rough | 2/1/2023 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 2/7/2023 | Partial Approval | RICHARD STEINBACH |
| Shower Pan | 2/27/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 3/1/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/10/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 4/10/2023 | Approved | BOBBY KEY |
| Green Building Rough | 4/10/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 4/18/2023 | Approved | BOBBY KEY |
| Final | 7/28/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 7/28/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 7/28/2023 | Approved | BOBBY KEY |
| Final | 1/24/2024 | Corrections Issued | BOBBY KEY |
| Final | 2/27/2024 | OK to Issue CofO | BOBBY KEY |