10214 N WESCOTT AVE 91040
Certificate Information: 10214 N WESCOTT AVE 91040
- Application / Permit
- 20014-20000-00716
- Plan Check / Job No.
- B20VN02706
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add 13' x 17' to enlarge existing bedroom and add a bathroom to single-family dwelling. All work per wood framed prescriptive provisions
- Permit Issued
- Issued on 2/18/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2020 | ANGELICA DAVE |
| Corrections Issued | 2/18/2020 | ANGELICA DAVE |
| Plan Check Approved | 2/18/2020 | ALYSSA N NARCISO |
| Issued | 2/18/2020 | LADBS |
| CofO in Progress | 9/23/2021 | WILLIAM KUEHN |
| Permit Finaled | 11/13/2021 | MICHAEL SMITH |
| CofO Issued | 11/13/2021 | MICHAEL SMITH |
| Permit Finaled | 11/13/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2020 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 2/18/2020 | BARTON HOLMES |
| Roof/Waste drainage to street | Cleared | 2/18/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/24/2020 | Not Ready for Inspection | PIERRE VEGA |
| Deputy Drilled-In Anchors | 2/27/2020 | Approved | BEAU COLLINS |
| Footing/Foundation/Slab | 2/27/2020 | Corrections Issued | BEAU COLLINS |
| Footing/Foundation/Slab | 3/6/2020 | Approved | BEAU COLLINS |
| Insulation | 3/12/2020 | Not Ready for Inspection | BEAU COLLINS |
| Insulation | 3/17/2020 | Corrections Issued | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2020 | Partial Approval | BEAU COLLINS |
| ELECTRICAL-Rough | 4/3/2020 | Not Ready for Inspection | BEAU COLLINS |
| Wood Frame | 4/3/2020 | Not Ready for Inspection | BEAU COLLINS |
| Wood Frame | 4/14/2020 | Corrections Issued | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2020 | Approved | BEAU COLLINS |
| Interior/Exterior Lathing | 4/22/2020 | Corrections Issued | BEAU COLLINS |
| Interior/Exterior Lathing | 4/24/2020 | Partial Approval | BEAU COLLINS |
| Rough-Elec/Plmb/HVAC | 4/24/2020 | Approved | BEAU COLLINS |
| Insulation | 4/29/2020 | Partial Approval | BEAU COLLINS |
| Drywall Nailing | 5/4/2020 | Partial Approval | BEAU COLLINS |
| Green Building Rough | 5/4/2020 | Approved | BEAU COLLINS |
| Insulation | 5/4/2020 | Approved | BEAU COLLINS |
| Interior/Exterior Lathing | 6/30/2020 | Approved | ROBERT MINASSIANS |
| BUILDING-Rough-Frame | 8/19/2020 | Approved | BEAU COLLINS |
| Drywall Nailing | 8/19/2020 | Approved | BEAU COLLINS |
| Final | 8/19/2020 | Not Ready for Inspection | BEAU COLLINS |
| HVAC-Final | 8/19/2020 | Approved | BEAU COLLINS |
| PLUMBING-Final | 8/19/2020 | Corrections Issued | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 8/19/2020 | SGSOV Not Ready | BEAU COLLINS |
| Smoke Detectors | 8/19/2020 | Approved | BEAU COLLINS |
| Final | 1/28/2021 | No Access for Inspection | BEAU COLLINS |
| Green Building Final | 1/28/2021 | No Access for Inspection | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 1/28/2021 | SGSOV Not Ready | BEAU COLLINS |
| Final | 2/3/2021 | Not Ready for Inspection | BEAU COLLINS |
| Green Building Final | 2/3/2021 | Not Ready for Inspection | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 2/3/2021 | SGSOV Not Ready | BEAU COLLINS |
| Final | 2/8/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 2/8/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/8/2021 | SGSOV Not Ready | JOHN HAYES |
| Final | 3/16/2021 | Corrections Issued | BEAU COLLINS |
| Green Building Final | 3/16/2021 | Not Ready for Inspection | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 3/16/2021 | SGSOV Approved | BEAU COLLINS |
| Final | 9/22/2021 | OK to Issue CofO | WILLIAM KUEHN |
| Green Building Final | 9/22/2021 | Approved | WILLIAM KUEHN |
| PLUMBING-Final | 9/22/2021 | Approved | WILLIAM KUEHN |