7030 N TYRONE AVE 91405
Certificate Information: 7030 N TYRONE AVE 91405
- Application / Permit
- 20014-20000-00715
- Plan Check / Job No.
- B20VN02702
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 18'-0" x 24'-10" ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 2/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/8/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2020 | SARKIS HARABEDIAN |
| Corrections Issued | 2/18/2020 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 2/19/2020 | APPLICANT |
| Plan Check Approved | 2/24/2020 | SARKIS HARABEDIAN |
| Issued | 2/24/2020 | LADBS |
| CofO in Progress | 7/23/2020 | WILLIAM KUEHN |
| CofO Issued | 8/8/2020 | MICHAEL SMITH |
| Permit Finaled | 8/8/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 2/21/2020 | JOHN TRIANTAFYLLOS |
| Hold | Cleared | 3/11/2020 | LOURDES RAMIRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wassef,, Mena Maher Salama; Lic. No.: C84979 | 28131 VALERIO CT VALENCIA, CA 91354 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/9/2020 | Partial Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/13/2020 | Conditional Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/29/2020 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2020 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2020 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 6/17/2020 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/23/2020 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2020 | Approved | DANIEL DREW |
| Green Building Rough | 6/23/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 6/30/2020 | Partial Approval | MISAEL ESPARZA |
| Insulation | 7/2/2020 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 7/8/2020 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 7/13/2020 | Approved | MISAEL ESPARZA |
| Final | 7/22/2020 | OK to Issue CofO | WILLIAM KUEHN |
| Footing/Foundation/Slab | 7/22/2020 | Approved | WILLIAM KUEHN |
| Green Building Final | 7/22/2020 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 7/22/2020 | SGSOV Approved | WILLIAM KUEHN |
| Smoke Detectors | 7/22/2020 | Approved | WILLIAM KUEHN |