4542 N MORELLA AVE 91607

Certificate Information: 4542 N MORELLA AVE 91607

Application / Permit
20014-20000-00706
Plan Check / Job No.
B20VN02684
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO REBUILD 40' X 38' OF (E) BUILDING FOOTPRINT, 22'-7" X 38' ADDITION AND CREATE 2ND-STORY TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. ADD 13' X 5'-7" ATTACHED PATIO COVER & 6'-6" X 10' TRELLIS. FIRE SPRINKLER REQUIRED NFPA-13D.
Permit Issued
Issued on 8/12/2020
Issuing Office
Current Status
CofO Issued on 3/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 ABDUL CHEGENI
Corrections Issued 3/9/2020 ABDUL CHEGENI
Green Plans Picked Up 3/9/2020 APPLICANT
Quality Review Completed 3/10/2020 STEVEN KIM
Building Plans Picked Up 3/11/2020 APPLICANT
Applicant returned to address corrections 7/2/2020 SERGIO MUNIZ
Applicant returned to address corrections 8/3/2020 SERGIO MUNIZ
Plan Check Approved 8/12/2020 SERGIO MUNIZ
Issued 8/12/2020 APPLICANT
CofO in Progress 3/10/2021 DANIEL ORRANTE
Permit Finaled 3/25/2021 MICHAEL SMITH
CofO Issued 3/25/2021 MICHAEL SMITH
Permit Finaled 3/25/2021 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 4/9/2020 DAVID MATSON
Address approval Cleared 4/14/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/14/2020 ADRIAN CASTRO
Permit Cleared 4/14/2020 ADRIAN CASTRO
Sewer availability Cleared 4/14/2020 ADRIAN CASTRO
ZI Cleared 5/14/2020 DANIEL CORONADO
Low Impact Development Cleared 6/18/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 7/6/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 7/16/2020 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Azarbin,, Hamid Reza; Lic. No.: C64515 22655 COVELLO ST      WEST HILLS, CA 91307

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/25/2020 Approved THOMAS FINNILA
PLUMBING-Rough 9/1/2020 Partial Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 9/2/2020 Partial Approval THOMAS FINNILA
Deputy Steel/Welding 9/10/2020 Approved DANIEL ORRANTE
Footing/Foundation/Slab 9/11/2020 Approved DANIEL DREW
BUILDING-Rough-Frame 9/25/2020 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/7/2020 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/13/2020 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/15/2020 Conditional Approval THOMAS FINNILA
Rough-Elec/Plmb/HVAC 10/16/2020 Partial Approval THOMAS FINNILA
Shower Pan 10/19/2020 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 10/21/2020 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/21/2020 Corrections Issued THOMAS FINNILA
HVAC-Rough 10/21/2020 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 10/21/2020 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 10/26/2020 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/26/2020 Conditional Approval THOMAS FINNILA
Interior/Exterior Lathing 10/30/2020 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 11/4/2020 Partial Inspection THOMAS FINNILA
Green Building Rough 11/4/2020 Partial Inspection THOMAS FINNILA
HVAC-Rough 11/4/2020 Partial Approval THOMAS FINNILA
Insulation 11/4/2020 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 11/4/2020 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 11/10/2020 Conditional Approval THOMAS FINNILA
Green Building Rough 11/10/2020 Approved THOMAS FINNILA
HVAC-Rough 11/10/2020 Approved THOMAS FINNILA
HVAC-Rough 11/16/2020 Approved THOMAS FINNILA
Insulation 11/16/2020 Approved THOMAS FINNILA
MERV13>=Rough 11/16/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 11/19/2020 Approved THOMAS FINNILA
Drywall Nailing 11/20/2020 Approved THOMAS FINNILA
HVAC-Final 1/26/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 2/2/2021 Approved THOMAS FINNILA
HVAC-Final 2/17/2021 Conditional Approval THOMAS FINNILA
PLUMBING-Final 2/17/2021 Approved THOMAS FINNILA
BUILDING-Rough-Frame 2/22/2021 Approved THOMAS FINNILA
HVAC-Final 2/22/2021 Approved THOMAS FINNILA
Smoke Detectors 2/22/2021 Corrections Issued THOMAS FINNILA
Final 3/9/2021 OK to Issue CofO DANIEL ORRANTE
Green Building Final 3/9/2021 Approved DANIEL ORRANTE
MERV13>=Final 3/9/2021 Approved DANIEL ORRANTE
SGSOV-Seismic Gas S/O Valve 3/9/2021 SGSOV Approved DANIEL ORRANTE
Smoke Detectors 3/9/2021 Approved DANIEL ORRANTE