10521 N JOHANNA AVE 91040
Certificate Information: 10521 N JOHANNA AVE 91040
- Application / Permit
- 20014-20000-00695
- Plan Check / Job No.
- B20VN02652
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- IRR SHAPED ADDITION ( 745 SF) AT REAR AND FRONT OF (E) ACCESSORY LIVING QUARTERS AND CONVERT TO NEW 20'-3.5" z 53'-9" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). AUTOMATIC SPRINKLER SYSTEM IS REQUIRED.
- Permit Issued
- Issued on 6/3/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/14/2020 | APPLICANT |
| Green Plans Picked Up | 2/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | SEAN SHAHMIRI |
| Corrections Issued | 3/7/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 3/10/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 3/12/2020 | APPLICANT |
| Applicant returned to address corrections | 11/2/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 11/4/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 2/17/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 3/17/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 4/29/2022 | SEAN SHAHMIRI |
| Issued | 6/3/2022 | APPLICANT |
| CofO in Progress | 4/28/2023 | DAVID ANDERSON |
| CofO Issued | 8/17/2023 | RUBEN SALAS |
| Permit Finaled | 8/17/2023 | RUBEN SALAS |
Permit Application Clearance Information
| ZA Case | Cleared | 6/18/2020 | RICHARD REASER |
| Address approval | Cleared | 6/24/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2020 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 12/24/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 12/24/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 12/24/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 12/24/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/24/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 1/11/2021 | BRIAN MILLER |
| ZI | Cleared | 4/1/2021 | PEGGY MALONE-BROWN |
| Hydrant and Access approval | Cleared | 5/20/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 1/4/2022 | SAHIL SHARMA |
| Roof/Waste drainage to street | Cleared | 2/11/2022 | JOHN LIN |
| Green Code | Cleared | 3/15/2022 | AARON COSTA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abkarian,, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/30/2022 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 9/8/2022 | Approved | DAVID ANDERSON |
| Gas Test | 10/12/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 10/12/2022 | Partial Approval | DAVID ANDERSON |
| Underground Mechanical | 10/12/2022 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2022 | Partial Approval | DAVID ANDERSON |
| Insulation | 10/20/2022 | Partial Approval | DAVID ANDERSON |
| Underground Mechanical | 11/17/2022 | Partial Approval | DAVID ANDERSON |
| Deputy Wood Construction | 11/22/2022 | Conditional Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 12/28/2022 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 12/28/2022 | Corrections Issued | DAVID ANDERSON |
| HVAC-Rough | 12/28/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 12/28/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 12/28/2022 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 1/4/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/4/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 1/4/2023 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 1/4/2023 | Approved | DAVID ANDERSON |
| Insulation | 1/10/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 1/17/2023 | Approved | DAVID ANDERSON |
| Gas Test | 1/31/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 1/31/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 1/31/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 4/26/2023 | Approved | DAVID ANDERSON |
| Final | 4/26/2023 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 4/26/2023 | Approved | DAVID ANDERSON |
| HVAC-Final | 4/26/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 4/26/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 4/26/2023 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 4/26/2023 | Approved | DAVID ANDERSON |
| Final | 4/28/2023 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 4/28/2023 | SGSOV Approved | DAVID ANDERSON |