5907 N ENCINO AVE 91316
Certificate Information: 5907 N ENCINO AVE 91316
- Application / Permit
- 20014-20000-00671
- Plan Check / Job No.
- B20VN02544
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (2) BEDROOMS, (2) BATHROOMS, 1/2 BATH, FAMILY & DINING ROOM TO REAR OF (E) 1-STORY SFD W/ ATTACHED GARAGE; RELOCATE (E) KITCHEN; INTERIOR REMODEL
- Permit Issued
- Issued on 8/26/2020
- Issuing Office
- Current Status
- CofO Issued on 10/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2020 | APPLICANT |
| Green Plans Picked Up | 2/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/9/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 3/11/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 3/12/2020 | APPLICANT |
| Plan Check Approved | 8/6/2020 | NILOOFAR MEHRAIN |
| Issued | 8/26/2020 | APPLICANT |
| CofO in Progress | 10/6/2021 | STEVEN BACK |
| Permit Finaled | 10/7/2021 | MICHAEL SMITH |
| CofO Issued | 10/7/2021 | MICHAEL SMITH |
| Permit Finaled | 10/7/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 4/2/2020 | AARON COSTA |
| Low Impact Development | Cleared | 6/16/2020 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 6/22/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 6/22/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 7/20/2020 | KURT CORRAL |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: C24587 | 21243 VENTURA BLVD #115 WOODLAND HILLS, CA 91364 |
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/28/2020 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 9/1/2020 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 9/4/2020 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 9/4/2020 | Not Ready for Inspection | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 9/9/2020 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 9/9/2020 | Not Ready for Inspection | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 9/14/2020 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 9/14/2020 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 9/16/2020 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 9/16/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 9/29/2020 | Partial Approval | STEVEN BACK |
| Insulation | 9/29/2020 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 9/29/2020 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2020 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 10/30/2020 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2020 | Corrections Issued | STEVEN BACK |
| Pre-Inspection | 10/30/2020 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2020 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 12/3/2020 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 12/11/2020 | Approved | STEVEN BACK |
| Deputy Wood Construction | 12/15/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 12/23/2020 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 12/23/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2020 | Approved | STEVEN BACK |
| Green Building Rough | 12/23/2020 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 12/23/2020 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 2/10/2021 | Approved | STEVEN BACK |
| Green Building Rough | 2/10/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 2/10/2021 | Approved | STEVEN BACK |
| Insulation | 2/18/2021 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 2/18/2021 | Approved | STEVEN BACK |
| Shower Pan | 2/18/2021 | Approved | STEVEN BACK |
| Insulation | 2/25/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Insulation | 3/2/2021 | Approved | STEVEN BACK |
| Final | 6/24/2021 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 6/24/2021 | Approved | STEVEN BACK |
| Green Building Final | 6/24/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 6/24/2021 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 6/24/2021 | Approved | STEVEN BACK |
| Final | 8/10/2021 | Corrections Issued | STEVEN BACK |
| Final | 8/30/2021 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Final | 10/6/2021 | Approved | STEVEN BACK |
| Final | 10/6/2021 | OK to Issue CofO | STEVEN BACK |
| Service/Power Release | 10/6/2021 | Approved | STEVEN BACK |