22149 W SCHOOLCRAFT ST 91303

Certificate Information: 22149 W SCHOOLCRAFT ST 91303

Application / Permit
20014-20000-00665
Plan Check / Job No.
B20VN02534
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel and 20' x 23' addition to single family dwelling for new bdrm and bthrm and to relocate an existing bthrm and laundry. All work per engineer.
Permit Issued
Issued on 2/20/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 ANGELICA DAVE
Corrections Issued 2/13/2020 ANGELICA DAVE
Plan Check Approved 2/20/2020 ANGELICA MARTINEZ
Issued 2/20/2020 LADBS
CofO in Progress 11/22/2020 TROY SANDERS
CofO Issued 11/24/2020 JOHN JANSON
Permit Finaled 11/24/2020 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/20/2020 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 2/20/2020 APEKSHYA BAJRACHARYA
Sewer availability Cleared 2/20/2020 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/27/2020 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 3/3/2020 Approved JOHN KIDWELL
BUILDING-Rough-Frame 3/11/2020 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 3/11/2020 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 3/11/2020 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 3/17/2020 Partial Approval JOHN KIDWELL
PLUMBING-Rough 3/17/2020 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 4/15/2020 Partial Approval HENRY KIM
Green Building Rough 4/15/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 5/8/2020 Not Ready for Inspection DONALD SUNSERI
Green Building Rough 5/8/2020 Not Ready for Inspection DONALD SUNSERI
HVAC-Rough 5/8/2020 Approved DONALD SUNSERI
PLUMBING-Rough 5/8/2020 Approved DONALD SUNSERI
BUILDING-Rough-Frame 5/15/2020 Approved JOHN KIDWELL
ELECTRICAL-Rough 5/15/2020 Approved JOHN KIDWELL
Green Building Rough 5/15/2020 Approved JOHN KIDWELL
Insulation 5/22/2020 Approved JOHN KIDWELL
Interior/Exterior Lathing 5/22/2020 Not Ready for Inspection JOHN KIDWELL
Drywall Nailing 6/2/2020 Approved JOHN KIDWELL
Interior/Exterior Lathing 6/10/2020 Partial Approval MICHAEL TEMPLE
Shower Pan 6/10/2020 Approved MICHAEL TEMPLE
ELECTRICAL-Final 10/21/2020 Approved TROY SANDERS
Final 10/21/2020 Corrections Issued TROY SANDERS
Green Building Final 10/21/2020 Corrections Issued TROY SANDERS
HVAC-Final 10/21/2020 Approved TROY SANDERS
PLUMBING-Final 10/21/2020 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 10/21/2020 SGSOV Approved TROY SANDERS
Smoke Detectors 10/21/2020 Approved TROY SANDERS
Final 11/20/2020 OK to Issue CofO TROY SANDERS
Green Building Final 11/20/2020 Approved TROY SANDERS