11811 W ALBERS ST 91607
Certificate Information: 11811 W ALBERS ST 91607
- Application / Permit
- 20014-20000-00662
- Plan Check / Job No.
- B20VN02526
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE 6' X 20'8" STORAGE ROOM , NEW 15' X 20'8" ADDITION TO AND CONVERT (E) 20'8" X 19' DETACHED GARAGE TO ACCESSORY DWELLING UNIT , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 6/15/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2020 | RARES BODEA |
| Corrections Issued | 2/15/2020 | RARES BODEA |
| Building Plans Picked Up | 2/19/2020 | APPLICANT |
| Plan Check Approved | 6/2/2020 | RARES BODEA |
| Issued | 6/15/2020 | LADBS |
| CofO in Progress | 2/11/2021 | ARAM AVEDISIAN |
| CofO Issued | 4/10/2021 | MICHAEL SMITH |
| Permit Finaled | 4/10/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/19/2020 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2020 | MARKOS PEREZ-BRAN |
| Miscellaneous | Cleared | 2/19/2020 | VINCENT QUITORIANO |
| Roof/Waste drainage to street | Cleared | 2/19/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 2/19/2020 | MARKOS PEREZ-BRAN |
| Construction near power lines | Cleared | 3/6/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/6/2020 | RIDWAN HARDY |
| Specific Plan | Cleared | 5/4/2020 | OLGA AYALA |
| ZI | Cleared | 5/4/2020 | OLGA AYALA |
Contact Information
| Contractor | California Construction Center Inc; Lic. No.: 891847-B | 12509 OXNARD #209 NORTH HOLLYWOOD, CA 91606 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/9/2020 | Approved | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/9/2020 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 7/21/2020 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/24/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Sewer | 7/24/2020 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/29/2020 | Conditional Approval | THOMAS FINNILA |
| Underground Mechanical | 7/29/2020 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2020 | Corrections Issued | THOMAS FINNILA |
| Deputy Wood Construction | 9/30/2020 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2020 | Partial Approval | THOMAS FINNILA |
| Gas Test | 10/2/2020 | Partial Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 10/30/2020 | No Access for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 11/2/2020 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 11/2/2020 | Approved | THOMAS FINNILA |
| Green Building Rough | 11/2/2020 | Approved | THOMAS FINNILA |
| HVAC-Rough | 11/2/2020 | Approved | THOMAS FINNILA |
| MERV13>=Rough | 11/2/2020 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 11/2/2020 | Approved | THOMAS FINNILA |
| Insulation | 11/9/2020 | Conditional Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/9/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 11/9/2020 | Approved | THOMAS FINNILA |
| Drywall Nailing | 11/17/2020 | Approved | THOMAS FINNILA |
| Insulation | 11/17/2020 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/17/2020 | Approved | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/4/2021 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 2/4/2021 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 2/4/2021 | Corrections Issued | THOMAS FINNILA |
| Final | 2/8/2021 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 2/8/2021 | Corrections Issued | THOMAS FINNILA |
| MERV13>=Final | 2/8/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 2/11/2021 | Approved | ARAM AVEDISIAN |
| Final | 2/11/2021 | OK to Issue CofO | ARAM AVEDISIAN |
| Green Building Final | 2/11/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 2/11/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 2/11/2021 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/11/2021 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 2/11/2021 | Approved | ARAM AVEDISIAN |
| Smoke Detectors | 2/11/2021 | Approved | ARAM AVEDISIAN |