11811 W ALBERS ST 91607

Certificate Information: 11811 W ALBERS ST 91607

Application / Permit
20014-20000-00662
Plan Check / Job No.
B20VN02526
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 6' X 20'8" STORAGE ROOM , NEW 15' X 20'8" ADDITION TO AND CONVERT (E) 20'8" X 19' DETACHED GARAGE TO ACCESSORY DWELLING UNIT , ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/15/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2020 APPLICANT
Assigned to Plan Check Engineer 2/14/2020 RARES BODEA
Corrections Issued 2/15/2020 RARES BODEA
Building Plans Picked Up 2/19/2020 APPLICANT
Plan Check Approved 6/2/2020 RARES BODEA
Issued 6/15/2020 LADBS
CofO in Progress 2/11/2021 ARAM AVEDISIAN
CofO Issued 4/10/2021 MICHAEL SMITH
Permit Finaled 4/10/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/19/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 2/19/2020 MARKOS PEREZ-BRAN
Miscellaneous Cleared 2/19/2020 VINCENT QUITORIANO
Roof/Waste drainage to street Cleared 2/19/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 2/19/2020 MARKOS PEREZ-BRAN
Construction near power lines Cleared 3/6/2020 RIDWAN HARDY
Construction within easement Cleared 3/6/2020 RIDWAN HARDY
Specific Plan Cleared 5/4/2020 OLGA AYALA
ZI Cleared 5/4/2020 OLGA AYALA

Contact Information

Contractor California Construction Center Inc; Lic. No.: 891847-B 12509 OXNARD #209      NORTH HOLLYWOOD, CA 91606
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/9/2020 Approved THOMAS FINNILA
Footing/Foundation/Slab 7/9/2020 Partial Approval THOMAS FINNILA
PLUMBING-Rough 7/21/2020 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 7/24/2020 Not Ready for Inspection THOMAS FINNILA
Sewer 7/24/2020 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 7/29/2020 Conditional Approval THOMAS FINNILA
Underground Mechanical 7/29/2020 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/28/2020 Corrections Issued THOMAS FINNILA
Deputy Wood Construction 9/30/2020 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/2/2020 Partial Approval THOMAS FINNILA
Gas Test 10/2/2020 Partial Approval THOMAS FINNILA
Deputy Drilled-In Anchors 10/30/2020 No Access for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 11/2/2020 Approved THOMAS FINNILA
ELECTRICAL-Rough 11/2/2020 Approved THOMAS FINNILA
Green Building Rough 11/2/2020 Approved THOMAS FINNILA
HVAC-Rough 11/2/2020 Approved THOMAS FINNILA
MERV13>=Rough 11/2/2020 Approved THOMAS FINNILA
PLUMBING-Rough 11/2/2020 Approved THOMAS FINNILA
Insulation 11/9/2020 Conditional Approval THOMAS FINNILA
Interior/Exterior Lathing 11/9/2020 Not Ready for Inspection THOMAS FINNILA
Shower Pan 11/9/2020 Approved THOMAS FINNILA
Drywall Nailing 11/17/2020 Approved THOMAS FINNILA
Insulation 11/17/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 11/17/2020 Approved THOMAS FINNILA
Footing/Foundation/Slab 2/4/2021 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 2/4/2021 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 2/4/2021 Corrections Issued THOMAS FINNILA
Final 2/8/2021 Corrections Issued THOMAS FINNILA
Green Building Final 2/8/2021 Corrections Issued THOMAS FINNILA
MERV13>=Final 2/8/2021 Approved THOMAS FINNILA
ELECTRICAL-Final 2/11/2021 Approved ARAM AVEDISIAN
Final 2/11/2021 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 2/11/2021 Approved ARAM AVEDISIAN
HVAC-Final 2/11/2021 Approved ARAM AVEDISIAN
PLUMBING-Final 2/11/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 2/11/2021 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 2/11/2021 Approved ARAM AVEDISIAN
Smoke Detectors 2/11/2021 Approved ARAM AVEDISIAN