6219 N KLUMP AVE 91606
Certificate Information: 6219 N KLUMP AVE 91606
- Application / Permit
- 20014-20000-00656
- Plan Check / Job No.
- B20VN02504
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-2" X 20'-2" DETACHED GARAGE AND ADD IRREGULAR 20'-0" X 41'-6" FOR (N) ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/11/2021
- Issuing Office
- Current Status
- CofO Issued on 1/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | JENNIFER LEE |
| Corrections Issued | 2/20/2020 | JENNIFER LEE |
| Plan Check Approved | 3/10/2020 | JEROME MAGAT PALMA |
| Issued | 3/11/2021 | APPLICANT |
| CofO in Progress | 11/12/2021 | DANIEL DREW |
| CofO Issued | 1/4/2022 | MICHAEL SMITH |
| Permit Finaled | 1/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2020 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2020 | JEANETTE VONG |
| Sewer availability | Cleared | 2/28/2020 | JEANETTE VONG |
| Low Impact Development | Cleared | 3/9/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 3/9/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 184 S ALTADENA DRIVE PASADENA, CA 91107 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/31/2021 | Conditional Approval | DANIEL DREW |
| PLUMBING-Rough | 3/31/2021 | Partial Approval | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2021 | Partial Approval | GREGG CUMMINGS |
| Wood Frame | 4/15/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/7/2021 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 5/7/2021 | Approved | MISAEL ESPARZA |
| Green Building Rough | 5/7/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 5/7/2021 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 5/7/2021 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2021 | Approved | DANIEL DREW |
| HVAC-Rough | 5/13/2021 | Approved | DANIEL DREW |
| Sewer | 5/13/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 5/18/2021 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/25/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 5/25/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/25/2021 | Approved | MATTHEW NELSON |
| Insulation | 6/1/2021 | Approved | MORRIS JACKSON |
| Drywall Nailing | 6/7/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/7/2021 | Approved | MORRIS JACKSON |
| Final | 8/19/2021 | Corrections Issued | DANIEL DREW |
| Footing/Foundation/Slab | 8/19/2021 | Approved | DANIEL DREW |
| Green Building Final | 8/19/2021 | Corrections Issued | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 8/19/2021 | SGSOV Approved | DANIEL DREW |
| Smoke Detectors | 8/19/2021 | Approved | DANIEL DREW |
| Final | 9/24/2021 | Corrections Issued | DANIEL DREW |
| Green Building Final | 9/24/2021 | Approved | DANIEL DREW |
| Final | 11/12/2021 | OK to Issue CofO | DANIEL DREW |
| Pre-Inspection | 11/17/2021 | Partial Approval | MATT KELLERMAN |
| Service/Power Release | 12/21/2021 | No Access for Inspection | MISAEL ESPARZA |
| Service/Power Release | 12/27/2021 | Approved | JACK KARGODORIAN |