11008 N ELDORA AVE 91040
Certificate Information: 11008 N ELDORA AVE 91040
- Application / Permit
- 20014-20000-00654
- Plan Check / Job No.
- B20VN02494
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 10'-0" x 5'-6" TO (E) DETACHED ONE CAR GARAGE AND CONVERT IT TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 11/19/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2020 | ALDOUS CHIC |
| Corrections Issued | 2/28/2020 | ALDOUS CHIC |
| Applicant returned to address corrections | 9/2/2020 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 10/28/2020 | SARKIS HARABEDIAN |
| Plan Check Approved | 11/16/2020 | SARKIS HARABEDIAN |
| Issued | 11/19/2020 | APPLICANT |
| CofO in Progress | 8/25/2021 | MATTHEW NELSON |
| Permit Finaled | 9/18/2021 | MICHAEL SMITH |
| CofO Issued | 9/18/2021 | MICHAEL SMITH |
| Permit Finaled | 9/18/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 2/28/2020 | GUILLERMO PETRA |
| Grading Pre-Inspection | Cleared | 9/30/2020 | VASIL MIHALEV |
| Low Impact Development | Cleared | 10/29/2020 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2020 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 11/10/2020 | ABDULLAH SADOZAI |
Contact Information
| Architect | Powell,, Gregory M; Lic. No.: C28099 | 9821 SHADOW ISLAND DR. SHADOW HILLS, CA 91040 |
| Contractor | Owner-Builder | , |
| Engineer | Diankov,, Nikolay Ivanov; Lic. No.: C52206 | 4529 ANGELES CREST HWY STE 105 LA CANADA, CA 91011 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/23/2020 | Partial Approval | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 11/23/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 2/12/2021 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/2/2021 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/2/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 3/2/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 3/2/2021 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 3/2/2021 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/10/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/10/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 3/10/2021 | Approved | MATTHEW NELSON |
| Insulation | 3/10/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 3/17/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/17/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/22/2021 | Approved | LILIANA PORTILLO |
| Pre-Inspection | 4/22/2021 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 7/9/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 7/9/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/9/2021 | Approved | MATTHEW NELSON |
| Green Building Final | 7/9/2021 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Final | 7/9/2021 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 7/9/2021 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 7/9/2021 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 7/9/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 8/9/2021 | No Access for Inspection | MATTHEW NELSON |
| Green Building Final | 8/9/2021 | No Access for Inspection | MATTHEW NELSON |
| Smoke Detectors | 8/9/2021 | No Access for Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 8/10/2021 | Corrections Issued | MATTHEW NELSON |
| Final | 8/10/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 8/10/2021 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 8/10/2021 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 8/10/2021 | Approved | MATTHEW NELSON |
| Smoke Detectors | 8/10/2021 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 8/13/2021 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Final | 8/25/2021 | Approved | MATTHEW NELSON |
| Final | 8/25/2021 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 8/25/2021 | Approved | MATTHEW NELSON |
| HVAC-Final | 8/25/2021 | Approved | MATTHEW NELSON |
| Smoke Detectors | 8/25/2021 | Approved | MATTHEW NELSON |