13941 W JUDD ST 91331

Certificate Information: 13941 W JUDD ST 91331

Application / Permit
20014-20000-00653
Plan Check / Job No.
B20VN02488
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
19' X 25' ADDITION TO (E) 1-STORY SFD
Permit Issued
Issued on 2/27/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/19/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2020 APPLICANT
Assigned to Plan Check Engineer 2/14/2020 PINANK PATEL
Corrections Issued 2/20/2020 PINANK PATEL
Building Plans Picked Up 2/21/2020 APPLICANT
Plan Check Approved 2/26/2020 PINANK PATEL
Issued 2/27/2020 LADBS
CofO in Progress 7/30/2020 DANIEL ORRANTE
CofO Issued 8/19/2020 MICHAEL SMITH
Permit Finaled 8/19/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/24/2020 JOSHUA DIAZ
Low Impact Development Cleared 2/24/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 2/24/2020 JOSHUA DIAZ
Sewer availability Cleared 2/25/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/27/2020 Approved MICHEL ABAJAN
Footing/Foundation/Slab 4/27/2020 Approved MICHEL ABAJAN
METHANE-Barrier 4/27/2020 Approved MICHEL ABAJAN
METHANE-Subgrade 4/27/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 5/7/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/7/2020 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 5/7/2020 Approved MICHEL ABAJAN
Wood Frame 5/7/2020 Approved MICHEL ABAJAN
Insulation 5/11/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/11/2020 Approved MICHEL ABAJAN
Drywall Nailing 5/13/2020 Approved MICHEL ABAJAN
Sewer 7/2/2020 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 7/22/2020 Not Ready for Inspection MICHEL ABAJAN
Final 7/22/2020 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 7/22/2020 Not Ready for Inspection MICHEL ABAJAN
Green Building Rough 7/22/2020 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Final 7/22/2020 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Rough 7/22/2020 Not Ready for Inspection MICHEL ABAJAN
METHANE-Final 7/22/2020 Not Ready for Inspection MICHEL ABAJAN
METHANE-Rough 7/22/2020 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/22/2020 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 7/22/2020 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 7/29/2020 Approved DANIEL ORRANTE
Final 7/29/2020 OK to Issue CofO DANIEL ORRANTE
Green Building Final 7/29/2020 Approved DANIEL ORRANTE
Green Building Rough 7/29/2020 Approved DANIEL ORRANTE
MERV13>=Final 7/29/2020 Approved DANIEL ORRANTE
MERV13>=Rough 7/29/2020 Approved DANIEL ORRANTE
METHANE-Final 7/29/2020 Approved DANIEL ORRANTE
METHANE-Rough 7/29/2020 Approved DANIEL ORRANTE
SGSOV-Seismic Gas S/O Valve 7/29/2020 SGSOV Approved DANIEL ORRANTE
Smoke Detectors 7/29/2020 Approved DANIEL ORRANTE