13939 W JUDD ST 91331
Certificate Information: 13939 W JUDD ST 91331
- Application / Permit
- 20014-20000-00652
- Plan Check / Job No.
- B20VN02487
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO (E) GARAGE AND REC. ROOM AND CONVERSION TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 2/27/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/19/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2020 | PINANK PATEL |
| Corrections Issued | 2/20/2020 | PINANK PATEL |
| Building Plans Picked Up | 2/21/2020 | APPLICANT |
| Plan Check Approved | 2/26/2020 | PINANK PATEL |
| Issued | 2/27/2020 | LADBS |
| CofO in Progress | 7/30/2020 | DANIEL ORRANTE |
| Permit Finaled | 8/19/2020 | MICHAEL SMITH |
| CofO Issued | 8/19/2020 | MICHAEL SMITH |
| Permit Finaled | 8/19/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2020 | JOSHUA DIAZ |
| Low Impact Development | Cleared | 2/24/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 2/24/2020 | JOSHUA DIAZ |
| Sewer availability | Cleared | 2/25/2020 | ADRIAN CASTRO |
| Address approval | Cleared | 2/26/2020 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Rough | 4/27/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 5/6/2020 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/6/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Barrier | 5/6/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 5/6/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Subgrade | 5/6/2020 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 5/6/2020 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/11/2020 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 5/11/2020 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 5/11/2020 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2020 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 6/5/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| MERV13>=Rough | 6/5/2020 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 6/5/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/15/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/15/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 6/15/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 6/15/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 6/15/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/15/2020 | Approved | MICHEL ABAJAN |
| Insulation | 6/19/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/19/2020 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/23/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/21/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 7/21/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 7/21/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 7/21/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| MERV13>=Final | 7/21/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/21/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/21/2020 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 7/21/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 7/29/2020 | OK to Issue CofO | DANIEL ORRANTE |
| Green Building Final | 7/29/2020 | Approved | DANIEL ORRANTE |
| SGSOV-Seismic Gas S/O Valve | 7/29/2020 | SGSOV Approved | DANIEL ORRANTE |
| Smoke Detectors | 7/29/2020 | Approved | DANIEL ORRANTE |