72' X 47'-9"IRREGULAR SHAPE ADDITION TO (E) SINGLE FAMILY DWELLING. MAJOR REMODEL. SPRINKLER REQUIRED NFPA 13D.
Permit Issued
Issued on 6/10/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 SERGIO MUNIZ
Corrections Issued 3/9/2020 SERGIO MUNIZ
Quality Review Completed 3/11/2020 STEVEN KIM
Building Plans Picked Up 3/11/2020 APPLICANT
Green Plans Picked Up 3/11/2020 APPLICANT
Plan Check Approved 6/2/2020 SERGIO MUNIZ
Issued 6/10/2020 LADBS
CofO in Progress 10/20/2020 JUAN VALENZUELA
CofO in Progress 10/20/2020 JUAN VALENZUELA
CofO in Progress 10/22/2020 JUAN VALENZUELA
CofO Issued 11/2/2020 VINCENT COTTON
Permit Finaled 11/2/2020 VINCENT COTTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/12/2020 JOHN LIN
Sewer availability Cleared 3/12/2020 JOHN LIN
Green Code Cleared 3/18/2020 MICHAEL AYERS
Specific Plan Cleared 3/25/2020 FREDDY GARCIA
Low Impact Development Cleared 5/13/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/22/2020 DINAH GARIN
GPI Written Notices Cleared 6/2/2020 SERGIO MUNIZ
Grading Pre-Inspection Cleared 6/2/2020 SERGIO MUNIZ

Contact Information

Architect Samson,, Charles Andrew H; Lic. No.: C22979 6119 MARY ELLEN AVENUE      VAN NUYS, CA 91401
Contractor Local Construction Remodeling; Lic. No.: 966738-B 14901 TUBA STREET      MISSION HILLS, CA 91345
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/25/2020 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/1/2020 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 7/1/2020 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 7/27/2020 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 7/30/2020 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/30/2020 Approved JUAN VALENZUELA
Green Building Rough 7/30/2020 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 7/30/2020 Corrections Issued JUAN VALENZUELA
BUILDING-Rough-Frame 8/4/2020 Approved JUAN VALENZUELA
ELECTRICAL-Rough 8/4/2020 Approved JUAN VALENZUELA
Green Building Rough 8/4/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 8/4/2020 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 8/4/2020 Approved JUAN VALENZUELA
Shower Pan 8/4/2020 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 8/4/2020 Approved JUAN VALENZUELA
HVAC-Rough 8/6/2020 Approved JUAN VALENZUELA
Insulation 8/6/2020 Approved JUAN VALENZUELA
Drywall Nailing 8/11/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 8/11/2020 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 8/18/2020 Approved JUAN VALENZUELA
ELECTRICAL-Final 10/1/2020 Not Ready for Inspection JOHNNY MIRANDA
Gas Test 10/1/2020 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Final 10/1/2020 Not Ready for Inspection JOHNNY MIRANDA
Service/Power Release 10/1/2020 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Final 10/7/2020 Corrections Issued JUAN VALENZUELA
HVAC-Final 10/7/2020 Approved JUAN VALENZUELA
PLUMBING-Final 10/7/2020 Corrections Issued JUAN VALENZUELA
Special/Order Compliance 10/7/2020 Approved PIERRE VEGA
ELECTRICAL-Final 10/9/2020 Approved JUAN VALENZUELA
Gas Test 10/9/2020 Approved JUAN VALENZUELA
PLUMBING-Final 10/9/2020 Approved JUAN VALENZUELA
Final 10/19/2020 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 10/19/2020 Approved JUAN VALENZUELA
Green Building Final 10/19/2020 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 10/19/2020 SGSOV Approved JUAN VALENZUELA
Service/Power Release 10/19/2020 Approved JUAN VALENZUELA
Smoke Detectors 10/19/2020 Approved JUAN VALENZUELA
Final 10/21/2020 OK to Issue CofO JUAN VALENZUELA