7919-7921 W MCGROARTY ST 91040

Certificate Information: 7919-7921 W MCGROARTY ST 91040

Application / Permit
20014-20000-00647
Plan Check / Job No.
B20VN02478
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Add 10'-3" x 11'-2" to and convert the attached garage into an Accessory Dwelling Unit. all work per wfpp.
Permit Issued
Issued on 2/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 ANGELICA DAVE
Corrections Issued 2/13/2020 ANGELICA DAVE
Plan Check Approved 2/13/2020 SARKIS HARABEDIAN
Issued 2/13/2020 LADBS
CofO in Progress 1/27/2023 DAVID ANDERSON
CofO Issued 2/7/2023 MICHAEL SMITH
Permit Finaled 2/7/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/13/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/13/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 2/13/2020 BARTON HOLMES
Roof/Waste drainage to street Cleared 2/13/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/13/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/3/2020 Approved BEAU COLLINS
Wood Frame 6/18/2020 Partial Inspection BEAU COLLINS
Wood Frame 7/8/2020 Partial Approval BEAU COLLINS
ELECTRICAL-Rough 9/21/2020 Approved BEAU COLLINS
PLUMBING-Rough 9/21/2020 Approved BEAU COLLINS
Drywall Nailing 12/10/2020 Not Ready for Inspection BEAU COLLINS
Green Building Rough 12/10/2020 Approved BEAU COLLINS
Insulation 12/10/2020 Approved BEAU COLLINS
Drywall Nailing 12/17/2020 Approved BEAU COLLINS
Shower Pan 12/17/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 1/12/2021 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 3/24/2021 Approved BEAU COLLINS
Final 3/24/2021 Corrections Issued BEAU COLLINS
Footing/Foundation/Slab 3/24/2021 Approved BEAU COLLINS
Green Building Final 3/24/2021 Not Ready for Inspection BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 3/24/2021 SGSOV Not Ready BEAU COLLINS
Smoke Detectors 3/24/2021 Not Ready for Inspection BEAU COLLINS
Final 4/30/2021 Corrections Issued BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 4/30/2021 SGSOV Not Ready BEAU COLLINS
Final 5/12/2021 Corrections Issued MATTHEW NELSON
Green Building Final 5/12/2021 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 5/12/2021 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 5/12/2021 Not Ready for Inspection MATTHEW NELSON
Final 1/20/2023 Corrections Issued DAVID ANDERSON
Green Building Final 1/20/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 1/20/2023 SGSOV Approved DAVID ANDERSON
Smoke Detectors 1/20/2023 Corrections Issued DAVID ANDERSON
Final 1/24/2023 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 1/24/2023 Approved DAVID ANDERSON
Final 1/26/2023 OK to Issue CofO DAVID ANDERSON