10932 W SAVONA ROAD 90077

Certificate Information: 10932 W SAVONA ROAD 90077

Application / Permit
20014-20000-00646
Plan Check / Job No.
B20VN02470
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 6'-4" X 11' PORTION OF GARAGE TO SINGLE FAMILY DWELLING; ADD 56'-7" X 24'-7" ON SECOND FLOOR; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/21/2020
Issuing Office
Current Status
CofO Issued on 11/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2020 APPLICANT
Green Plans Picked Up 2/27/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 SELLA BENYAMIN
Corrections Issued 3/10/2020 SELLA BENYAMIN
Quality Review Completed 3/12/2020 STEVEN KIM
Building Plans Picked Up 3/16/2020 APPLICANT
Applicant returned to address corrections 5/14/2020 SELLA BENYAMIN
Plan Check Approved 5/21/2020 SELLA BENYAMIN
Issued 5/21/2020 APPLICANT
CofO in Progress 10/28/2021 CHRISTOPHER WILSON
Permit Finaled 11/1/2021 DANIEL ORRANTE
CofO Issued 11/1/2021 DANIEL ORRANTE
Permit Finaled 11/1/2021 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/18/2020 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 3/18/2020 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 3/18/2020 GUILLERMO PETRA
Sewer availability Cleared 3/18/2020 GUILLERMO PETRA
Green Code Cleared 4/10/2020 MICHAEL AYERS
Eng Process Fee Ord 176,300 Cleared 4/29/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 5/8/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 5/12/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/11/2020 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 6/15/2020 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 6/17/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/24/2020 Partial Approval CARLOS MATAMOROS
Special/Order Compliance 8/1/2020 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 8/8/2020 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 8/29/2020 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 10/20/2020 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/20/2020 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 10/20/2020 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 10/23/2020 Approved CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/23/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 10/23/2020 Approved CHRISTOPHER WILSON
HVAC-Rough 11/4/2020 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 11/4/2020 Not Ready for Inspection CHRISTOPHER WILSON
Shower Pan 11/4/2020 Corrections Issued CHRISTOPHER WILSON
Shower Pan 11/6/2020 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 11/24/2020 Partial Approval MATT KELLERMAN
HVAC-Rough 12/4/2020 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 12/4/2020 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/7/2020 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/10/2020 Approved CHRISTOPHER WILSON
Green Building Rough 12/10/2020 Approved CHRISTOPHER WILSON
Insulation 12/10/2020 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 12/10/2020 Approved CHRISTOPHER WILSON
Drywall Nailing 12/22/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 12/22/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 3/6/2021 Partial Inspection CHRISTOPHER WILSON
Gas Test 5/28/2021 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 7/6/2021 Corrections Issued CHRISTOPHER WILSON
Final 7/6/2021 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 7/6/2021 Approved CHRISTOPHER WILSON
Green Building Final 7/6/2021 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Final 7/6/2021 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 7/6/2021 Partial Inspection AMY COLIN
SGSOV-Seismic Gas S/O Valve 7/6/2021 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 7/6/2021 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 7/16/2021 Approved CHRISTOPHER WILSON
Green Building Final 7/16/2021 Approved CHRISTOPHER WILSON
PLUMBING-Final 7/16/2021 Approved CHRISTOPHER WILSON
Pre-Inspection 7/16/2021 Partial Inspection ADAM ESCOTO
Final 9/3/2021 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 9/3/2021 Approved CHRISTOPHER WILSON
Final 10/26/2021 Conditional Approval CHRISTOPHER WILSON