7019 1/2 N ALABAMA AVE 91303

Certificate Information: 7019 1/2 N ALABAMA AVE 91303

Application / Permit
20014-20000-00645
Plan Check / Job No.
B20VN02466
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
13'-0" X 16'-3" ADDITION TO (E) SINGLE FAMILY DWELLING FOR NEW BEDROOM AND BATHROOM. WORK PER WFPP.
Permit Issued
Issued on 2/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/4/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 ROSENDO MEDINA
Issued 2/13/2020 LADBS
CofO in Progress 8/3/2020 HENRY KIM
Permit Finaled 8/4/2020 JOHN JANSON
CofO Issued 8/4/2020 JOHN JANSON
Permit Finaled 8/4/2020 JOHN JANSON

Permit Application Clearance Information

ZI Cleared 2/12/2020 HERMINIGILDO AGUSTIN
Eng Process Fee Ord 176,300 Cleared 2/13/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 2/13/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/13/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/18/2020 Corrections Issued HENRY KIM
Excavation/Setback/Form/Re-Bar 3/24/2020 Partial Approval HENRY KIM
BUILDING-Rough-Frame 4/21/2020 Partial Approval HENRY KIM
PLUMBING-Rough 4/21/2020 Corrections Issued HENRY KIM
Underground Mechanical 4/21/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 5/4/2020 Partial Approval HENRY KIM
Footing/Foundation/Slab 5/4/2020 Approved HENRY KIM
Insulation 5/4/2020 Partial Approval HENRY KIM
PLUMBING-Rough 5/4/2020 Partial Approval HENRY KIM
Sewer 5/4/2020 Approved HENRY KIM
ELECTRICAL-Rough 5/19/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 5/19/2020 Partial Approval HENRY KIM
BUILDING-Rough-Frame 5/28/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 5/28/2020 Approved HENRY KIM
Green Building Rough 5/28/2020 Approved HENRY KIM
Rough-Elec/Plmb/HVAC 5/28/2020 Approved HENRY KIM
Shower Pan 5/28/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/15/2020 Approved HENRY KIM
Insulation 6/15/2020 Approved HENRY KIM
Interior/Exterior Lathing 6/15/2020 Approved HENRY KIM
Drywall Nailing 6/19/2020 Approved HENRY KIM
Interior/Exterior Lathing 6/19/2020 Approved HENRY KIM
ELECTRICAL-Final 8/3/2020 Approved HENRY KIM
Final 8/3/2020 OK to Issue CofO HENRY KIM
Green Building Final 8/3/2020 Approved HENRY KIM
HVAC-Final 8/3/2020 Approved HENRY KIM
PLUMBING-Final 8/3/2020 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 8/3/2020 SGSOV Approved HENRY KIM
Smoke Detectors 8/3/2020 Approved HENRY KIM