1855-1861 S MANSFIELD AVE 90019
Certificate Information: 1855-1861 S MANSFIELD AVE 90019
- Application / Permit
- 20014-20000-00643
- Plan Check / Job No.
- B20VN02464
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 13' X 20' 1ST FLOOR ADDITION TO (E) APARTMENT TO CREATE A NEW BEDROOM , BATHROOM AND CLOSET, SPLIT (E) 2ND FLOOR UNIT INTO 2 UNITS TO CREATE A 4 UNIT APARTMENT , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 9/12/2022
- Issuing Office
- Valley
- Current Status
- Issued on 9/12/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | RARES BODEA |
| Corrections Issued | 3/7/2020 | RARES BODEA |
| Quality Review Completed | 3/11/2020 | GUANG MIN TUNG |
| Green Plans Picked Up | 4/18/2022 | APPLICANT |
| Applicant returned to address corrections | 5/18/2022 | RARES BODEA |
| Applicant returned to address corrections | 6/6/2022 | RARES BODEA |
| Applicant returned to address corrections | 7/22/2022 | RARES BODEA |
| Plan Check Approved | 9/12/2022 | RARES BODEA |
| Issued | 9/12/2022 | APPLICANT |
| Building Plans Picked Up | 10/4/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/14/2020 | CELINA MORENO |
| Highway dedication | Cleared | 12/14/2020 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 12/14/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2020 | CELINA MORENO |
| Sewer availability | Cleared | 12/15/2020 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 12/18/2020 | KURT CORRAL |
| Frnt yard landscape/Water mgmt | Cleared | 2/24/2021 | MINDY NGUYEN |
| Tenant Habitability Plan | Cleared | 3/7/2022 | RICHARD BRINSON |
| Green Code | Cleared | 4/15/2022 | RARES BODEA |
Contact Information
| Contractor | Bella Development Llc; Lic. No.: 1081661-B | 13330 BLOOMFIELD AVE STE 220 NORWALK, CA 90650 |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/26/2022 | Partial Inspection | KATY RAMIREZ |
| Green Building Rough | 11/15/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 11/15/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Deputy Drilled-In Anchors | 12/13/2022 | Partial Approval | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wall Anchors | 1/4/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2023 | Partial Approval | ALFREDO LOPEZ |
| Green Building Rough | 11/28/2023 | Not Ready for Inspection | RICARDO ROBLES |
| Wood Frame | 11/28/2023 | Partial Approval | RICARDO ROBLES |
| Green Building Rough | 4/12/2024 | Not Ready for Inspection | JACOB MYERS |
| Wood Frame | 4/12/2024 | Partial Approval | JACOB MYERS |
| Drywall Nailing | 7/22/2026 | Approved | IAN BLINN |
| Final | 7/22/2026 | Not Ready for Inspection | IAN BLINN |
| Footing/Foundation/Slab | 7/22/2026 | Not Ready for Inspection | IAN BLINN |
| Green Building Final | 7/22/2026 | Approved | IAN BLINN |
| Green Building Rough | 7/22/2026 | Approved | IAN BLINN |
| Reinforced Concrete Frame | 7/22/2026 | Not Ready for Inspection | IAN BLINN |
| SGSOV-Seismic Gas S/O Valve | 7/22/2026 | SGSOV Approved | IAN BLINN |
| Smoke Detectors | 7/22/2026 | Approved | IAN BLINN |
| Wood Frame | 7/22/2026 | Approved | IAN BLINN |