949 E IMPERIAL HWY 90059

Certificate Information: 949 E IMPERIAL HWY 90059

Application / Permit
20014-20000-00639
Plan Check / Job No.
B20VN02452
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
19'-6" X 21'-9" IRREG SHAPED ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 3/4/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2020 APPLICANT
Assigned to Plan Check Engineer 2/14/2020 JEROME MAGAT PALMA
Corrections Issued 2/17/2020 JEROME MAGAT PALMA
Building Plans Picked Up 2/18/2020 APPLICANT
Plan Check Approved 2/27/2020 JEROME MAGAT PALMA
Issued 3/4/2020 LADBS
CofO in Progress 8/27/2020 EUGENE CASSIDY
Permit Finaled 10/23/2020 DEROLD HAUFF
CofO Issued 10/23/2020 DEROLD HAUFF
Permit Finaled 10/23/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/19/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/19/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 2/19/2020 JEANIE LAM
Sewer availability Cleared 2/19/2020 JEANIE LAM
Community Plan Implem. Overlay Cleared 3/4/2020 HELEN JADALI
ZI Cleared 3/4/2020 HELEN JADALI

Contact Information

Contractor Victor Orozco Construction; Lic. No.: 982481-B 126 W J STREET      ONTARIO, CA 91762

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/24/2020 Approved BRIAN CHRISTIAN
PLUMBING-Rough 3/24/2020 Partial Approval BRIAN CHRISTIAN
Wood Frame 3/31/2020 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 4/2/2020 Not Ready for Inspection BRIAN CHRISTIAN
ELECTRICAL-Rough 4/2/2020 Not Ready for Inspection BRIAN CHRISTIAN
HVAC-Rough 4/2/2020 Not Ready for Inspection BRIAN CHRISTIAN
PLUMBING-Rough 4/2/2020 Not Ready for Inspection BRIAN CHRISTIAN
Sewer 4/2/2020 Not Ready for Inspection BRIAN CHRISTIAN
Interior/Exterior Lathing 4/3/2020 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 4/3/2020 Approved EUGENE CASSIDY
Wood Frame 4/3/2020 Approved EUGENE CASSIDY
Insulation 4/6/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 4/8/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 6/22/2020 Approved EUGENE CASSIDY
ELECTRICAL-Final 6/22/2020 Not Ready for Inspection EUGENE CASSIDY
Final 6/22/2020 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 6/22/2020 Approved EUGENE CASSIDY
Green Building Final 6/22/2020 Corrections Issued EUGENE CASSIDY
Green Building Rough 6/22/2020 Approved EUGENE CASSIDY
HVAC-Final 6/22/2020 Approved EUGENE CASSIDY
MERV13>=Final 6/22/2020 Approved EUGENE CASSIDY
MERV13>=Rough 6/22/2020 Approved EUGENE CASSIDY
PLUMBING-Final 6/22/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/22/2020 SGSOV Approved EUGENE CASSIDY
Service/Power Release 6/22/2020 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 6/22/2020 Approved EUGENE CASSIDY
Final 7/31/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 7/31/2020 Approved EUGENE CASSIDY
Final 8/27/2020 OK to Issue CofO EUGENE CASSIDY