949 E IMPERIAL HWY 90059
Certificate Information: 949 E IMPERIAL HWY 90059
- Application / Permit
- 20014-20000-00639
- Plan Check / Job No.
- B20VN02452
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 19'-6" X 21'-9" IRREG SHAPED ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 3/4/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/23/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 2/17/2020 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 2/18/2020 | APPLICANT |
| Plan Check Approved | 2/27/2020 | JEROME MAGAT PALMA |
| Issued | 3/4/2020 | LADBS |
| CofO in Progress | 8/27/2020 | EUGENE CASSIDY |
| Permit Finaled | 10/23/2020 | DEROLD HAUFF |
| CofO Issued | 10/23/2020 | DEROLD HAUFF |
| Permit Finaled | 10/23/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/19/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 2/19/2020 | JEANIE LAM |
| Sewer availability | Cleared | 2/19/2020 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 3/4/2020 | HELEN JADALI |
| ZI | Cleared | 3/4/2020 | HELEN JADALI |
Contact Information
| Contractor | Victor Orozco Construction; Lic. No.: 982481-B | 126 W J STREET ONTARIO, CA 91762 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/24/2020 | Approved | BRIAN CHRISTIAN |
| PLUMBING-Rough | 3/24/2020 | Partial Approval | BRIAN CHRISTIAN |
| Wood Frame | 3/31/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/2/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| ELECTRICAL-Rough | 4/2/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| HVAC-Rough | 4/2/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| PLUMBING-Rough | 4/2/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Sewer | 4/2/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 4/3/2020 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 4/3/2020 | Approved | EUGENE CASSIDY |
| Wood Frame | 4/3/2020 | Approved | EUGENE CASSIDY |
| Insulation | 4/6/2020 | Approved | BRIAN CHRISTIAN |
| Drywall Nailing | 4/8/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/22/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 6/22/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 6/22/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/22/2020 | Approved | EUGENE CASSIDY |
| Green Building Final | 6/22/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 6/22/2020 | Approved | EUGENE CASSIDY |
| HVAC-Final | 6/22/2020 | Approved | EUGENE CASSIDY |
| MERV13>=Final | 6/22/2020 | Approved | EUGENE CASSIDY |
| MERV13>=Rough | 6/22/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 6/22/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/22/2020 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 6/22/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 6/22/2020 | Approved | EUGENE CASSIDY |
| Final | 7/31/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/31/2020 | Approved | EUGENE CASSIDY |
| Final | 8/27/2020 | OK to Issue CofO | EUGENE CASSIDY |