13115 N GLENOAKS BLVD 91342
Certificate Information: 13115 N GLENOAKS BLVD 91342
- Application / Permit
- 20014-20000-00630
- Plan Check / Job No.
- B20VN02408
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 15' X 33' 3" ADDITION TO REAR AND INTERIOR REMODEL TO (E) KITCHEN OF SFD. ALL WORK DONE PER ENGINEERING. SEE COMMENTS
- Permit Issued
- Issued on 3/10/2020
- Issuing Office
- Valley
- Current Status
- Issued on 3/10/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/12/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 2/12/2020 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 3/2/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 3/10/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 3/10/2020 | JENNIFER LEE |
| Issued | 3/10/2020 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 3/10/2020 | GUILLERMO PETRA |
Contact Information
| Architect | Brisley,, Lawrence Kevin; Lic. No.: C19394 | 11560 NORTHDALE DRIVE MOORPARK, CA 93021 |
| Contractor | Owner-Builder | , |
| Engineer | Judd,, Shane Dennis; Lic. No.: C70991 | 17 E HIGH ST STE A MOORPARK, CA 93021 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/4/2021 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/20/2021 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/26/2021 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2021 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/7/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2021 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 7/20/2021 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/20/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 7/20/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/19/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 8/19/2021 | Approved | MATTHEW NELSON |
| Insulation | 8/19/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/1/2021 | Partial Approval | ADAM ESCOTO |
| Drywall Nailing | 9/22/2021 | Approved | JOHN HAYES |
| HVAC-Rough | 12/10/2021 | Approved | JOHN HAYES |
| Final | 5/30/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 5/30/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/30/2023 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 5/30/2023 | Approved | ARAM AVEDISIAN |