19452 W CITRONIA ST 91324
Certificate Information: 19452 W CITRONIA ST 91324
- Application / Permit
- 20014-20000-00627
- Plan Check / Job No.
- B20VN02399
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Add irr. 23'-7" x 35'-8" to and convert the detached garage into an Accessory Dwelling Unit
- Permit Issued
- Issued on 1/25/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/12/2020 | ANGELICA DAVE |
| Corrections Issued | 2/12/2020 | ANGELICA DAVE |
| Applicant returned to address corrections | 6/1/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 11/5/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 11/6/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 12/18/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 12/29/2020 | HAYATO TSUCHIYA |
| Issued | 1/25/2021 | APPLICANT |
| CofO in Progress | 11/23/2021 | JEFFREY PARD |
| Permit Finaled | 11/24/2021 | MICHAEL SMITH |
| CofO Issued | 11/24/2021 | MICHAEL SMITH |
| Permit Finaled | 11/24/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/2/2020 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2020 | JOHN LIN |
| Low Impact Development | Cleared | 5/15/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 5/20/2020 | ADRIAN CASTRO |
| Private sewage disp. approval | Cleared | 10/21/2020 | PATRICK MISCHLICH |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | A List Builders Inc; Lic. No.: 952112-B | 13237 CHANDLER BLVD SHERMAN OAKS, CA 91401 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/9/2021 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 2/9/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 2/9/2021 | Corrections Issued | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/8/2021 | Partial Approval | JEFFREY PARD |
| ELECTRICAL-Rough | 3/8/2021 | Corrections Issued | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 3/8/2021 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 3/8/2021 | Corrections Issued | JEFFREY PARD |
| Rough-Elec/Plmb/HVAC | 3/17/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/25/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 3/25/2021 | Not Ready for Inspection | JEFFREY PARD |
| Interior/Exterior Lathing | 3/25/2021 | Approved | JEFFREY PARD |
| Gas Test | 4/27/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 4/27/2021 | Approved | JEFFREY PARD |
| Shower Pan | 4/27/2021 | Approved | JEFFREY PARD |
| Drywall Nailing | 6/4/2021 | Approved | LILIANA PORTILLO |
| Green Building Rough | 6/4/2021 | Approved | LILIANA PORTILLO |
| Final | 9/3/2021 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 9/3/2021 | Corrections Issued | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 9/3/2021 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 9/3/2021 | Approved | JEFFREY PARD |
| Final | 11/3/2021 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Final | 11/3/2021 | Not Ready for Inspection | JEFFREY PARD |
| Final | 11/9/2021 | OK to Issue CofO | JEFFREY PARD |
| Green Building Final | 11/9/2021 | Approved | JEFFREY PARD |