16012 W WYANDOTTE ST 91406
Certificate Information: 16012 W WYANDOTTE ST 91406
- Application / Permit
- 20014-20000-00625
- Plan Check / Job No.
- B20VN02389
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 18' 9" 2-CAR GARAGE TO ACCESSORY DWELLING UNIT, ADD 26' X 24' 6" TO ACCESSORY DWELLING UNIT WITH ATTACHED 6' X 15' 3" OPEN TRELLIS. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 2/27/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/26/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/12/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 2/12/2020 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 2/14/2020 | APPLICANT |
| Plan Check Approved | 2/26/2020 | GURUNATH NESARAJAH |
| Issued | 2/27/2020 | LADBS |
| CofO in Progress | 10/1/2020 | MICHEL ABAJAN |
| Permit Finaled | 10/26/2020 | MICHAEL SMITH |
| CofO Issued | 10/26/2020 | MICHAEL SMITH |
| Permit Finaled | 10/26/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/19/2020 | WALTER RAMIREZ |
| Address approval | Cleared | 2/20/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 2/20/2020 | SARAH YOUSSEF |
| Sewer availability | Cleared | 2/20/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 2/21/2020 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/10/2020 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 3/12/2020 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 3/13/2020 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 3/16/2020 | Approved | ROBERT MINASSIANS |
| Footing/Foundation/Slab | 3/16/2020 | Corrections Issued | ROBERT MINASSIANS |
| Footing/Foundation/Slab | 3/19/2020 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 3/25/2020 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2020 | Partial Approval | DONALD SUNSERI |
| Green Building Rough | 3/25/2020 | Not Ready for Inspection | DONALD SUNSERI |
| Deputy Drilled-In Anchors | 4/2/2020 | Conditional Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 4/16/2020 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/16/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2020 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 4/16/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 4/16/2020 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 4/16/2020 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/21/2020 | Approved | MATTHEW NELSON |
| HVAC-Rough | 4/21/2020 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/21/2020 | Partial Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/23/2020 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/23/2020 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/23/2020 | Approved | MATTHEW NELSON |
| Insulation | 4/28/2020 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 4/28/2020 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 5/4/2020 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 5/4/2020 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 5/6/2020 | Approved | GREGG CUMMINGS |
| Final | 6/26/2020 | Corrections Issued | BEAU COLLINS |
| Green Building Final | 6/26/2020 | Not Ready for Inspection | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 6/26/2020 | SGSOV Not Ready | BEAU COLLINS |
| Smoke Detectors | 6/26/2020 | Approved | BEAU COLLINS |
| Final | 7/8/2020 | Corrections Issued | DANIEL DREW |
| Green Building Final | 7/8/2020 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 7/8/2020 | SGSOV Approved | DANIEL DREW |
| Final | 9/18/2020 | Corrections Issued | MICHEL ABAJAN |
| Final | 10/1/2020 | OK to Issue CofO | MICHEL ABAJAN |