4541 N LARKWOOD AVE 91364

Certificate Information: 4541 N LARKWOOD AVE 91364

Application / Permit
20014-20000-00622
Plan Check / Job No.
B20VN02377
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
16'-6" X 17'-1" ADDITION OF A BEDROOM AND BATHROOM TO THE (E) SINGLE FAMILY DWELLNG
Permit Issued
Issued on 3/3/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/31/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2020 APPLICANT
Assigned to Plan Check Engineer 2/11/2020 SERGIO MUNIZ
Corrections Issued 2/18/2020 SERGIO MUNIZ
Plan Check Approved 3/3/2020 HAYATO TSUCHIYA
Issued 3/3/2020 LADBS
CofO in Progress 7/18/2020 MICHAEL TEMPLE
Permit Finaled 7/31/2020 DONALD SUNSERI
CofO Issued 7/31/2020 DONALD SUNSERI
Permit Finaled 7/31/2020 DONALD SUNSERI

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/11/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 2/11/2020 ADRIAN CASTRO
Sewer availability Cleared 2/11/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 2/13/2020 BARTON HOLMES

Contact Information

Contractor High Touch Inc; Lic. No.: 860365-B 10917 WEST PICO BOULEVARD      LOS ANGELES, CA 90064
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/24/2020 Approved DONALD SUNSERI
Sewer 3/27/2020 Approved DAVID SANDOVAL
Underground Mechanical 3/27/2020 Partial Approval DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 4/1/2020 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 4/13/2020 Not Ready for Inspection DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 4/22/2020 Approved MICHAEL TEMPLE
BUILDING-Rough-Frame 5/8/2020 Partial Approval MICHAEL TEMPLE
ELECTRICAL-Rough 5/8/2020 Corrections Issued MICHAEL TEMPLE
Green Building Rough 5/8/2020 Not Ready for Inspection MICHAEL TEMPLE
PLUMBING-Rough 5/8/2020 Approved MICHAEL TEMPLE
ELECTRICAL-Rough 5/18/2020 Not Ready for Inspection DAVID SANDOVAL
Interior/Exterior Lathing 5/18/2020 Partial Approval DAVID SANDOVAL
Insulation 5/20/2020 Approved RONALD COWAN
BUILDING-Rough-Frame 5/22/2020 Approved MICHAEL TEMPLE
Drywall Nailing 5/22/2020 Approved MICHAEL TEMPLE
Rough-Elec/Plmb/HVAC 5/22/2020 Approved MICHAEL TEMPLE
Interior/Exterior Lathing 5/28/2020 Approved MICHAEL TEMPLE
Shower Pan 5/28/2020 Approved MICHAEL TEMPLE
Final 6/26/2020 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 6/26/2020 Not Ready for Inspection DAVID SANDOVAL
Green Building Final 6/26/2020 Not Ready for Inspection DAVID SANDOVAL
Green Building Rough 6/26/2020 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 6/26/2020 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 6/26/2020 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 6/30/2020 Approved MICHAEL TEMPLE
Final 6/30/2020 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 6/30/2020 Approved MICHAEL TEMPLE
Green Building Final 6/30/2020 Approved MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 6/30/2020 SGSOV Approved MICHAEL TEMPLE
Smoke Detectors 6/30/2020 Approved MICHAEL TEMPLE
ELECTRICAL-Final 7/17/2020 Approved DAVID SANDOVAL
Final 7/17/2020 OK to Issue CofO DAVID SANDOVAL
HVAC-Final 7/17/2020 Approved DAVID SANDOVAL
PLUMBING-Final 7/17/2020 Approved DAVID SANDOVAL