15045 W POLK ST 91342
Certificate Information: 15045 W POLK ST 91342
- Application / Permit
- 20014-20000-00614
- Plan Check / Job No.
- B20VN02350
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 17'5" x 28'10" ADDITION TO (E) SINGLE FAMILY DWELLING FOR TWO NEW BEDROOMS AND BATHROOMS. ALL WORK PER WFPP.
- Permit Issued
- Issued on 7/27/2022
- Issuing Office
- Current Status
- CofO Issued on 5/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2020 | ROSENDO MEDINA |
| Corrections Issued | 2/11/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 5/22/2020 | LUIS RINCON |
| Applicant returned to address corrections | 6/8/2020 | LUIS RINCON |
| Plan Check Approved | 6/8/2020 | LUIS RINCON |
| No Progress | 6/9/2020 | LUIS RINCON |
| Plan Check Approved | 7/12/2022 | LUIS RINCON |
| Building Plans Picked Up | 7/14/2022 | APPLICANT |
| Issued | 7/27/2022 | APPLICANT |
| CofO in Progress | 5/19/2025 | KEVIN BERBERYAN |
| Permit Finaled | 5/27/2025 | RUBEN SALAS |
| CofO Issued | 5/27/2025 | RUBEN SALAS |
| Permit Finaled | 5/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 8/12/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 4/28/2022 | ORVAL HERNANDEZ-MARCI |
| Grading Pre-Inspection | Cleared | 6/22/2022 | LANNY MERRICK |
| Roof/Waste drainage to street | Cleared | 7/1/2022 | JOHN LIN |
| GPI Written Notices | Cleared | 7/12/2022 | ROSENDO MEDINA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/30/2022 | Partial Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/16/2022 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/22/2022 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 9/22/2022 | Partial Approval | ASHLEY THOMPSON |
| Deputy Drilled-In Anchors | 9/23/2022 | Conditional Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 9/26/2022 | Approved | ARAM AVEDISIAN |
| Pre-Inspection | 10/26/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/23/2022 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/23/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Rough | 11/23/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/23/2022 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/5/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/5/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 12/5/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 12/5/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/5/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/19/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 1/19/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Approved | ARAM AVEDISIAN |
| Green Building Final | 3/8/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 3/8/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/5/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 4/5/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/5/2023 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 5/25/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 7/5/2023 | Approved | WILLIAM WREN |
| Insulation | 7/5/2023 | Not Ready for Inspection | WILLIAM WREN |
| Interior/Exterior Lathing | 7/5/2023 | Not Ready for Inspection | WILLIAM WREN |
| Pre-Inspection | 7/5/2023 | Not Ready for Inspection | WILLIAM WREN |
| Interior/Exterior Lathing | 8/3/2023 | Corrections Issued | MICHEL ABAJAN |
| Interior/Exterior Lathing | 8/9/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 12/5/2023 | Approved | KEVIN BERBERYAN |
| Shower Pan | 12/5/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 8/7/2024 | Approved | KEVIN BERBERYAN |
| Final | 8/7/2024 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 8/7/2024 | Approved | KEVIN BERBERYAN |
| Green Building Final | 8/7/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Final | 8/7/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 8/7/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 8/7/2024 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 8/7/2024 | Approved | KEVIN BERBERYAN |
| Final | 5/19/2025 | OK to Issue CofO | KEVIN BERBERYAN |