8538 N OSO AVE 91306

Certificate Information: 8538 N OSO AVE 91306

Application / Permit
20014-20000-00597
Plan Check / Job No.
B20VN02304
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Add 14'-6" x 27'-3" to and convert the detached accessory living quarters into an Accessory Dwelling Unit
Permit Issued
Issued on 2/12/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2020 APPLICANT
Assigned to Plan Check Engineer 2/11/2020 ANGELICA DAVE
Corrections Issued 2/11/2020 ANGELICA DAVE
Plan Check Approved 2/12/2020 HAYATO TSUCHIYA
Issued 2/12/2020 LADBS
CofO in Progress 10/17/2022 CHRIS CHRISTENSEN
Permit Finaled 10/28/2022 JOHN JANSON
CofO Issued 10/28/2022 JOHN JANSON
Permit Finaled 10/28/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/11/2020 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 2/11/2020 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 2/11/2020 APEKSHYA BAJRACHARYA
Sewer availability Cleared 2/11/2020 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/27/2020 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 3/3/2020 Not Ready for Inspection DONALD SUNSERI
Footing/Foundation/Slab 3/11/2020 Corrections Issued DAVID STEPANYAN
Footing/Foundation/Slab 3/17/2020 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Partial Approval DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Partial Approval DAVID STEPANYAN
Wood Frame 4/28/2020 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 5/13/2020 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 5/18/2020 Partial Approval DAVID STEPANYAN
Sewer 5/18/2020 Approved DAVID STEPANYAN
ELECTRICAL-Rough 5/27/2020 Approved DAVID STEPANYAN
HVAC-Rough 5/27/2020 Corrections Issued DAVID STEPANYAN
BUILDING-Rough-Frame 6/2/2020 Approved DAVID STEPANYAN
Green Building Rough 6/2/2020 Approved DAVID STEPANYAN
HVAC-Rough 6/2/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 6/2/2020 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 6/2/2020 Approved DAVID STEPANYAN
Insulation 6/8/2020 Approved DAVID STEPANYAN
Drywall Nailing 6/16/2020 Approved DAVID STEPANYAN
ELECTRICAL-Final 7/21/2021 Corrections Issued DAVID STEPANYAN
Final 7/21/2021 Corrections Issued DAVID STEPANYAN
Gas Test 7/21/2021 Corrections Issued DAVID STEPANYAN
Green Building Final 7/21/2021 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 7/21/2021 SGSOV Approved DAVID STEPANYAN
Shower Pan 7/21/2021 Corrections Issued DAVID STEPANYAN
Smoke Detectors 7/21/2021 Approved DAVID STEPANYAN
Final 11/4/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Final 11/4/2021 Approved DAVID STEPANYAN
Final 3/22/2022 Corrections Issued CHRIS CHRISTENSEN
Enclosure/Fence 7/29/2022 Corrections Issued CHRIS CHRISTENSEN
Final 7/29/2022 Corrections Issued CHRIS CHRISTENSEN
Gas Test 7/29/2022 Corrections Issued CHRIS CHRISTENSEN
Shower Pan 7/29/2022 Partial Approval CHRIS CHRISTENSEN
Final 10/14/2022 OK to Issue CofO CHRIS CHRISTENSEN