8759 N AQUEDUCT AVE 91343
Certificate Information: 8759 N AQUEDUCT AVE 91343
- Application / Permit
- 20014-20000-00596
- Plan Check / Job No.
- B20VN02303
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Add 8'-6" x 14'-9" to and convert the detached recreation room into an Accessory Dwelling Unit PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 10/18/2021
- Issuing Office
- Current Status
- CofO Issued on 2/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2020 | ANGELICA DAVE |
| Corrections Issued | 2/11/2020 | ANGELICA DAVE |
| Applicant returned to address corrections | 5/14/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 10/9/2020 | RAPHAEL ROSAS |
| Issued | 10/18/2021 | APPLICANT |
| CofO in Progress | 1/27/2022 | RAUL OLAGI |
| Permit Finaled | 2/5/2022 | MICHAEL SMITH |
| CofO Issued | 2/5/2022 | MICHAEL SMITH |
| Permit Finaled | 2/5/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 2/11/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/25/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/1/2021 | Partial Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 11/5/2021 | Approved | RAUL OLAGI |
| Pre-Inspection | 11/5/2021 | Partial Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 11/18/2021 | Corrections Issued | ALAN MORELOS |
| PLUMBING-Rough | 11/18/2021 | Not Ready for Inspection | ALAN MORELOS |
| ELECTRICAL-Rough | 12/9/2021 | Approved | ALAN MORELOS |
| Insulation | 12/9/2021 | Corrections Issued | ALAN MORELOS |
| HVAC-Rough | 12/20/2021 | Partial Inspection | RAUL OLAGI |
| Insulation | 12/20/2021 | Approved | RAUL OLAGI |
| Drywall Nailing | 1/12/2022 | Approved | ALAN MORELOS |
| Gas Test | 1/12/2022 | Approved | ALAN MORELOS |
| PLUMBING-Rough | 1/12/2022 | Approved | ALAN MORELOS |
| Final | 1/19/2022 | Corrections Issued | RAUL OLAGI |
| Wood Frame | 1/19/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/26/2022 | Approved | RAUL OLAGI |
| Final | 1/26/2022 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 1/26/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 1/26/2022 | Approved | RAUL OLAGI |
| MERV13>=Final | 1/26/2022 | Approved | RAUL OLAGI |
| MERV13>=Rough | 1/26/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/26/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 1/26/2022 | Approved | RAUL OLAGI |