12773 W BROOKLAKE ST 90066

Certificate Information: 12773 W BROOKLAKE ST 90066

Application / Permit
20014-20000-00594
Plan Check / Job No.
B20VN02291
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (29'-7"x 21'-8") IRR SHAPE @ FRONT & (7'-0"x 19'-10") @ REAR AND INT REMODEL TO (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
Permit Issued
Issued on 8/4/2020
Issuing Office
Current Status
CofO Issued on 5/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 TROY DEGUZMAN
Corrections Issued 3/17/2020 TROY DEGUZMAN
Quality Review Completed 3/20/2020 CHON CHIO KUO
Building Plans Picked Up 4/17/2020 APPLICANT
Applicant returned to address corrections 6/17/2020 TROY DEGUZMAN
Plan Check Approved 8/4/2020 TROY DEGUZMAN
Issued 8/4/2020 APPLICANT
CofO in Progress 5/18/2023 JESUS RODRIGUEZ
Permit Finaled 5/20/2023 DANIEL ORRANTE
CofO Issued 5/20/2023 DANIEL ORRANTE
Permit Finaled 5/20/2023 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 5/27/2020 MATTHEW CRAIG
Green Code Cleared 6/16/2020 MICHAEL AYERS
Grading Pre-Inspection Cleared 6/17/2020 TROY DEGUZMAN
Low Impact Development Cleared 6/30/2020 ANDRES COVARRUBIAS
Sewer availability Cleared 7/23/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/24/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 7/31/2020 DINAH GARIN

Contact Information

Contractor I N D Construction Inc; Lic. No.: 937833-B 17941 VENTURA BLVD. #205      ENCINO, CA 91316
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/9/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 9/25/2020 Corrections Issued ENRIQUE MIRELES
Green Building Rough 9/25/2020 Not Ready for Inspection ENRIQUE MIRELES
Underground Mechanical 9/25/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 9/28/2020 Partial Inspection DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 10/1/2020 Partial Approval ENRIQUE MIRELES
BUILDING-Rough-Frame 11/10/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 11/10/2020 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/10/2020 Corrections Issued ENRIQUE MIRELES
Green Building Rough 11/10/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 11/10/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 11/16/2020 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/16/2020 Partial Approval ENRIQUE MIRELES
Green Building Rough 11/16/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 11/16/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 12/17/2020 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/17/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 12/17/2020 Approved ENRIQUE MIRELES
Drywall Nailing 1/6/2021 Approved ENRIQUE MIRELES
Insulation 1/6/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 5/11/2021 Not Ready for Inspection ENRIQUE MIRELES
Service/Power Release 5/11/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 6/22/2021 Approved DONALD GALLAGHER
Final 7/26/2021 Corrections Issued ANTHONY MCDOWALL
Footing/Foundation/Slab 7/26/2021 Approved ANTHONY MCDOWALL
Green Building Final 7/26/2021 Not Ready for Inspection ANTHONY MCDOWALL
SGSOV-Seismic Gas S/O Valve 7/26/2021 SGSOV Approved ANTHONY MCDOWALL
Smoke Detectors 7/26/2021 Corrections Issued ANTHONY MCDOWALL
Final 5/10/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 5/10/2023 Approved JESUS RODRIGUEZ
Smoke Detectors 5/10/2023 Approved JESUS RODRIGUEZ
Final 5/18/2023 OK to Issue CofO JESUS RODRIGUEZ