12773 W BROOKLAKE ST 90066
Certificate Information: 12773 W BROOKLAKE ST 90066
- Application / Permit
- 20014-20000-00594
- Plan Check / Job No.
- B20VN02291
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (29'-7"x 21'-8") IRR SHAPE @ FRONT & (7'-0"x 19'-10") @ REAR AND INT REMODEL TO (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
- Permit Issued
- Issued on 8/4/2020
- Issuing Office
- Current Status
- CofO Issued on 5/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | TROY DEGUZMAN |
| Corrections Issued | 3/17/2020 | TROY DEGUZMAN |
| Quality Review Completed | 3/20/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 4/17/2020 | APPLICANT |
| Applicant returned to address corrections | 6/17/2020 | TROY DEGUZMAN |
| Plan Check Approved | 8/4/2020 | TROY DEGUZMAN |
| Issued | 8/4/2020 | APPLICANT |
| CofO in Progress | 5/18/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 5/20/2023 | DANIEL ORRANTE |
| CofO Issued | 5/20/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/20/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/27/2020 | MATTHEW CRAIG |
| Green Code | Cleared | 6/16/2020 | MICHAEL AYERS |
| Grading Pre-Inspection | Cleared | 6/17/2020 | TROY DEGUZMAN |
| Low Impact Development | Cleared | 6/30/2020 | ANDRES COVARRUBIAS |
| Sewer availability | Cleared | 7/23/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 7/31/2020 | DINAH GARIN |
Contact Information
| Contractor | I N D Construction Inc; Lic. No.: 937833-B | 17941 VENTURA BLVD. #205 ENCINO, CA 91316 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/9/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 9/25/2020 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 9/25/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 9/25/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/28/2020 | Partial Inspection | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2020 | Partial Approval | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/10/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/10/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2020 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 11/10/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/10/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/16/2020 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2020 | Partial Approval | ENRIQUE MIRELES |
| Green Building Rough | 11/16/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/16/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/17/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/17/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/17/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/6/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 1/6/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 5/11/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Service/Power Release | 5/11/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 6/22/2021 | Approved | DONALD GALLAGHER |
| Final | 7/26/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 7/26/2021 | Approved | ANTHONY MCDOWALL |
| Green Building Final | 7/26/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| SGSOV-Seismic Gas S/O Valve | 7/26/2021 | SGSOV Approved | ANTHONY MCDOWALL |
| Smoke Detectors | 7/26/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Final | 5/10/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 5/10/2023 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 5/10/2023 | Approved | JESUS RODRIGUEZ |
| Final | 5/18/2023 | OK to Issue CofO | JESUS RODRIGUEZ |