15025 W DEL GADO DR 91403
Certificate Information: 15025 W DEL GADO DR 91403
- Application / Permit
- 20014-20000-00582
- Plan Check / Job No.
- B20VN02233
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (5'-0"x 21'-0") BALCONY @ REAR & ENCLOSE PATIO WITH INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
- Permit Issued
- Issued on 4/6/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2020 | APPLICANT |
| Green Plans Picked Up | 2/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | TROY DEGUZMAN |
| Corrections Issued | 3/1/2020 | TROY DEGUZMAN |
| Quality Review Completed | 3/5/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/6/2020 | APPLICANT |
| Plan Check Approved | 3/26/2020 | TROY DEGUZMAN |
| Issued | 4/6/2020 | LADBS |
| CofO in Progress | 12/9/2022 | ROBERT GOLD |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2020 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 3/9/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 3/9/2020 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 3/16/2020 | DAVID MATSON |
Contact Information
| Architect | Perella,, Ryan Adam; Lic. No.: C30833 | 606 N LARCHMONT BLVD # 4A LOS ANGELES, CA 90004 |
| Contractor | Rener Construction & Design Inc; Lic. No.: 903760-B | 2103 CHEAM AVE SIMI VALLEY, CA 93063 |
| Engineer | Sayah,, Daniel Hoshyar; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 4/24/2020 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 4/27/2020 | Approved | TROY SANDERS |
| HVAC-Rough | 4/27/2020 | Approved | TROY SANDERS |
| PLUMBING-Rough | 4/27/2020 | Not Ready for Inspection | TROY SANDERS |
| Interior/Exterior Lathing | 5/6/2020 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 5/7/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 5/11/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 5/11/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/12/2020 | Approved | TROY SANDERS |
| Green Building Rough | 5/12/2020 | Approved | TROY SANDERS |
| Insulation | 5/14/2020 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 5/20/2020 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 6/9/2020 | Partial Approval | THOMAS FINNILA |
| Shower Pan | 6/9/2020 | Approved | THOMAS FINNILA |
| Drywall Nailing | 8/17/2020 | Approved | CHARLES POWELL |
| Final | 8/17/2020 | Corrections Issued | CHARLES POWELL |
| Footing/Foundation/Slab | 8/17/2020 | Approved | CHARLES POWELL |
| Green Building Final | 8/17/2020 | Approved | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 8/17/2020 | SGSOV Not Ready | CHARLES POWELL |
| Smoke Detectors | 8/17/2020 | Approved | CHARLES POWELL |
| Final | 8/19/2020 | Partial Approval | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 8/19/2020 | SGSOV Approved | CHARLES POWELL |
| Final | 12/7/2022 | OK to Issue CofO | ROBERT GOLD |