6843 N BALBOA BLVD 91406

Certificate Information: 6843 N BALBOA BLVD 91406

Application / Permit
20014-20000-00577
Plan Check / Job No.
B20VN02213
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD IRREGULAR SHAPE 19' X 24'-8" TO 18' X 20' DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 3/12/2021
Issuing Office
Metro
Current Status
CofO Issued on 1/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2020 APPLICANT
Assigned to Plan Check Engineer 2/10/2020 ALDOUS CHIC
Corrections Issued 2/10/2020 ALDOUS CHIC
Applicant returned to address corrections 9/14/2020 RICHARD GARCIA
Plan Check Approved 10/23/2020 RAPHAEL ROSAS
Issued 3/12/2021 APPLICANT
CofO in Progress 12/16/2021 SEAN HAUPT
Permit Finaled 1/6/2022 MICHAEL SMITH
CofO Issued 1/6/2022 MICHAEL SMITH
Permit Finaled 1/6/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/10/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/10/2020 JOHN TRIANTAFYLLOS
Permit Cleared 2/10/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 2/10/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/10/2020 JOHN TRIANTAFYLLOS
Construction within easement Cleared 8/27/2020 RIDWAN HARDY

Contact Information

Contractor D H Property Maintenance Inc; Lic. No.: 985811-B 11312 COVELLO STREET      SUN VALLEY, CA 91352

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/19/2021 Partial Approval STEVEN BACK
Deputy Drilled-In Anchors 4/22/2021 Partial Approval STEVEN BACK
Footing/Foundation/Slab 4/26/2021 Approved JEFFREY PARD
ELECTRICAL-Rough 6/1/2021 Corrections Issued STEVEN BACK
PLUMBING-Rough 6/1/2021 Corrections Issued STEVEN BACK
Sewer 6/1/2021 Approved STEVEN BACK
Underground Mechanical 6/1/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/9/2021 Approved STEVEN BACK
ELECTRICAL-Rough 6/17/2021 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/17/2021 Approved STEVEN BACK
HVAC-Rough 6/17/2021 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 6/17/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 6/17/2021 Approved STEVEN BACK
ELECTRICAL-Rough 6/24/2021 Approved STEVEN BACK
Green Building Rough 6/24/2021 Approved STEVEN BACK
HVAC-Rough 6/24/2021 Approved STEVEN BACK
Interior/Exterior Lathing 6/24/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 6/29/2021 Corrections Issued STEPHANIE SWANSON
Green Building Rough 6/29/2021 Approved STEPHANIE SWANSON
Insulation 6/29/2021 Corrections Issued STEPHANIE SWANSON
Insulation 7/6/2021 Approved STEPHANIE SWANSON
Drywall Nailing 7/13/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/13/2021 Approved RYAN SALAZAR
BUILDING-Rough-Frame 10/14/2021 Approved DAVID SANDOVAL
Final 10/14/2021 Corrections Issued DAVID SANDOVAL
Green Building Final 10/14/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV Approved DAVID SANDOVAL
Smoke Detectors 10/14/2021 Approved DAVID SANDOVAL
Final 11/22/2021 Conditional Approval SEAN HAUPT
Service/Power Release 12/2/2021 Approved SEAN HAUPT