7231 N ENFIELD AVE 91335
Certificate Information: 7231 N ENFIELD AVE 91335
- Application / Permit
- 20014-20000-00569
- Plan Check / Job No.
- B20VN02194
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) CARPORT AND STORAGE TO ACCESSORY DWEELING UNIT
- Permit Issued
- Issued on 3/2/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/9/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2020 | ALDOUS CHIC |
| Corrections Issued | 2/10/2020 | ALDOUS CHIC |
| Applicant returned to address corrections | 2/14/2020 | ARTIN ZARUKIAN |
| Plan Check Approved | 3/2/2020 | ALYSSA N NARCISO |
| Issued | 3/2/2020 | LADBS |
| CofO in Progress | 8/26/2020 | VINCENT HANLEY |
| Permit Finaled | 9/9/2020 | DONALD SUNSERI |
| CofO Issued | 9/9/2020 | DONALD SUNSERI |
| Permit Finaled | 9/9/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Address approval | Cleared | 2/10/2020 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2020 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 2/10/2020 | GEORGE SUCHAND |
| Roof/Waste drainage to street | Cleared | 2/10/2020 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 2/10/2020 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/4/2020 | Approved | VINCENT HANLEY |
| Gas Test | 5/4/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/4/2020 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/8/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/20/2020 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 5/20/2020 | Approved | VINCENT HANLEY |
| Shower Pan | 5/20/2020 | Approved | VINCENT HANLEY |
| Wood Frame | 5/20/2020 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/27/2020 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/27/2020 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2020 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 5/27/2020 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 5/27/2020 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/5/2020 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/5/2020 | Approved | VINCENT HANLEY |
| HVAC-Rough | 6/5/2020 | Approved | VINCENT HANLEY |
| Insulation | 6/18/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/18/2020 | Approved | VINCENT HANLEY |
| Drywall Nailing | 6/26/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/30/2020 | Approved | VINCENT HANLEY |
| Sewer | 6/30/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 8/19/2020 | Corrections Issued | VINCENT HANLEY |
| Final | 8/19/2020 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Final | 8/19/2020 | Approved | VINCENT HANLEY |
| HVAC-Final | 8/19/2020 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 8/19/2020 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/19/2020 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 8/19/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 8/26/2020 | Approved | VINCENT HANLEY |
| Final | 8/26/2020 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 8/26/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 8/26/2020 | Approved | VINCENT HANLEY |