116 W 69TH ST 90003

Certificate Information: 116 W 69TH ST 90003

Application / Permit
20014-20000-00568
Plan Check / Job No.
B20VN02190
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Add irr. 29'-6" x 32' to and convert the detached garage into an Accessory Dwelling Unit.
Permit Issued
Issued on 2/21/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 10/7/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2020 APPLICANT
Assigned to Plan Check Engineer 2/10/2020 ANGELICA DAVE
Corrections Issued 2/10/2020 ANGELICA DAVE
Plan Check Approved 2/14/2020 HAYATO TSUCHIYA
Issued 2/21/2020 LADBS
CofO in Progress 6/26/2020 EUGENE CASSIDY
Permit Finaled 10/7/2020 DEROLD HAUFF
CofO Issued 10/7/2020 DEROLD HAUFF
Permit Finaled 10/7/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/14/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 2/14/2020 JUAN ASHTON
Low Impact Development Cleared 2/14/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/14/2020 JUAN ASHTON
Sewer availability Cleared 2/14/2020 JUAN ASHTON

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/12/2020 Corrections Issued EUGENE CASSIDY
Underground Mechanical 3/12/2020 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 3/16/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 3/16/2020 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 3/16/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 4/3/2020 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/3/2020 Partial Approval EUGENE CASSIDY
Green Building Rough 4/3/2020 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 4/16/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 4/16/2020 Approved EUGENE CASSIDY
Green Building Rough 4/16/2020 Approved EUGENE CASSIDY
HVAC-Rough 4/16/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 4/16/2020 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 4/20/2020 Approved EUGENE CASSIDY
Wood Frame 4/20/2020 Approved EUGENE CASSIDY
Insulation 4/23/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 4/23/2020 Approved EUGENE CASSIDY
Drywall Nailing 4/27/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/21/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Final 5/21/2020 Approved ROBERT MCDOWELL
Final 5/21/2020 Conditional Approval ROBERT MCDOWELL
Footing/Foundation/Slab 5/21/2020 Approved ROBERT MCDOWELL
Green Building Final 5/21/2020 Approved ROBERT MCDOWELL
HVAC-Final 5/21/2020 Approved ROBERT MCDOWELL
PLUMBING-Final 5/21/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 5/21/2020 SGSOV Approved ROBERT MCDOWELL
Service/Power Release 5/21/2020 Approved ROBERT MCDOWELL
Smoke Detectors 5/21/2020 Approved ROBERT MCDOWELL
Final 6/25/2020 OK to Issue CofO EUGENE CASSIDY