116 W 69TH ST 90003
Certificate Information: 116 W 69TH ST 90003
- Application / Permit
- 20014-20000-00568
- Plan Check / Job No.
- B20VN02190
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Add irr. 29'-6" x 32' to and convert the detached garage into an Accessory Dwelling Unit.
- Permit Issued
- Issued on 2/21/2020
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 10/7/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2020 | ANGELICA DAVE |
| Corrections Issued | 2/10/2020 | ANGELICA DAVE |
| Plan Check Approved | 2/14/2020 | HAYATO TSUCHIYA |
| Issued | 2/21/2020 | LADBS |
| CofO in Progress | 6/26/2020 | EUGENE CASSIDY |
| Permit Finaled | 10/7/2020 | DEROLD HAUFF |
| CofO Issued | 10/7/2020 | DEROLD HAUFF |
| Permit Finaled | 10/7/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/14/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2020 | JUAN ASHTON |
| Low Impact Development | Cleared | 2/14/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 2/14/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 2/14/2020 | JUAN ASHTON |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/12/2020 | Corrections Issued | EUGENE CASSIDY |
| Underground Mechanical | 3/12/2020 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 3/16/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 3/16/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Underground Mechanical | 3/16/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/3/2020 | Corrections Issued | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2020 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 4/3/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/16/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/16/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 4/16/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 4/16/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 4/16/2020 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 4/20/2020 | Approved | EUGENE CASSIDY |
| Wood Frame | 4/20/2020 | Approved | EUGENE CASSIDY |
| Insulation | 4/23/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/23/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 4/27/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/21/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 5/21/2020 | Approved | ROBERT MCDOWELL |
| Final | 5/21/2020 | Conditional Approval | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 5/21/2020 | Approved | ROBERT MCDOWELL |
| Green Building Final | 5/21/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 5/21/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 5/21/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 5/21/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 5/21/2020 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 5/21/2020 | Approved | ROBERT MCDOWELL |
| Final | 6/25/2020 | OK to Issue CofO | EUGENE CASSIDY |