5050 N GAVIOTA AVE 91436

Certificate Information: 5050 N GAVIOTA AVE 91436

Application / Permit
20014-20000-00558
Plan Check / Job No.
B20VN02150
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED (16'-10" X 21') ADDITION AND REMODEL FOR (N) BATHROOM TO (E) 1-STORY SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/9/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2020 APPLICANT
Assigned to Plan Check Engineer 2/11/2020 RAPHAEL ROSAS
Corrections Issued 2/11/2020 RAPHAEL ROSAS
Building Plans Picked Up 2/14/2020 APPLICANT
Plan Check Approved 2/26/2020 RAPHAEL ROSAS
Issued 4/9/2020 LADBS
CofO in Progress 11/19/2020 PETER FOLLING
Permit Finaled 11/21/2020 DONALD SUNSERI
CofO Issued 11/21/2020 DONALD SUNSERI
Permit Finaled 11/21/2020 DONALD SUNSERI

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/14/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 2/14/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/14/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Golden Touch Construction Inc; Lic. No.: 892123-B 461 JESSIE STREET      SAN FERNANDO, CA 91340
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 2828 COCHRAN STREET 321      SIMI VALLEY, CA 93065

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/26/2020 Partial Approval RONALD COWAN
Footing/Foundation/Slab 5/26/2020 Partial Approval RONALD COWAN
Footing/Foundation/Slab 6/8/2020 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 7/6/2020 Approved RONALD COWAN
BUILDING-Rough-Frame 7/21/2020 Partial Approval RONALD COWAN
ELECTRICAL-Rough 7/21/2020 Approved RONALD COWAN
Green Building Rough 7/21/2020 Approved RONALD COWAN
HVAC-Rough 7/21/2020 Approved RONALD COWAN
PLUMBING-Rough 7/21/2020 Approved RONALD COWAN
Shower Pan 7/23/2020 Approved RONALD COWAN
BUILDING-Rough-Frame 7/29/2020 Approved RONALD COWAN
Insulation 7/29/2020 Approved RONALD COWAN
Interior/Exterior Lathing 8/11/2020 Approved RONALD COWAN
Drywall Nailing 8/17/2020 Approved RONALD COWAN
ELECTRICAL-Final 11/2/2020 Approved RONALD COWAN
Final 11/2/2020 Corrections Issued RONALD COWAN
Green Building Final 11/2/2020 Approved RONALD COWAN
HVAC-Final 11/2/2020 Approved RONALD COWAN
PLUMBING-Final 11/2/2020 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 11/2/2020 SGSOV Approved RONALD COWAN
Smoke Detectors 11/2/2020 Approved RONALD COWAN
Final 11/17/2020 Partial Approval RONALD COWAN