8398-8400 N JASON AVE 91304
Certificate Information: 8398-8400 N JASON AVE 91304
- Application / Permit
- 20014-20000-00542
- Plan Check / Job No.
- B20VN02109
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 18' 2" X 27' 5" ACCESSORY DWELLING UNIT TO (E) SINGLE FAMILY DWELLING. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 2/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2020 | ANGELICA DAVE |
| Corrections Issued | 2/7/2020 | ANGELICA DAVE |
| Plan Check Approved | 2/24/2020 | GURUNATH NESARAJAH |
| Issued | 2/24/2020 | LADBS |
| CofO in Progress | 10/4/2021 | DAVID STEPANYAN |
| CofO in Progress | 10/4/2021 | DAVID STEPANYAN |
| Permit Finaled | 10/7/2021 | JOHN JANSON |
| CofO Issued | 10/7/2021 | JOHN JANSON |
| Permit Finaled | 10/7/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/7/2020 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 2/7/2020 | MARKOS PEREZ-BRAN |
| ZA Case | Cleared | 2/7/2020 | STEVEN WECHSLER |
| Low Impact Development | Cleared | 2/21/2020 | MARTIN FRAGOSO |
| Grading Pre-Inspection | Cleared | 2/24/2020 | ANGELICA MARTINEZ |
| Roof/Waste drainage to street | Cleared | 2/24/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | R S Carpentry Design & Remodeling Inc; Lic. No.: 1023757-B | 5737 KANEN RD STE 196 AGOURA HILLS, CA 91301 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/23/2020 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 3/27/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 4/1/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 4/13/2020 | Partial Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 4/16/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 4/28/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Rough | 4/28/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 4/28/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 5/1/2020 | Partial Approval | DAVID STEPANYAN |
| Green Building Rough | 5/1/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 5/1/2020 | Partial Approval | DAVID STEPANYAN |
| Insulation | 5/5/2020 | Partial Approval | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2020 | Corrections Issued | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2020 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 7/30/2020 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 7/30/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 7/30/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 7/30/2020 | Approved | DAVID STEPANYAN |
| Sewer | 7/30/2020 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 7/30/2020 | Partial Approval | DAVID STEPANYAN |
| Deputy Wood Construction | 7/31/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 8/13/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/5/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 10/5/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 10/5/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 10/5/2020 | Partial Approval | DAVID STEPANYAN |
| Shower Pan | 10/5/2020 | Approved | DAVID STEPANYAN |
| Insulation | 10/13/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 10/27/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 10/27/2020 | Approved | DAVID STEPANYAN |
| Final | 2/11/2021 | Corrections Issued | DAVID STEPANYAN |
| Green Building Final | 2/11/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 2/11/2021 | SGSOV Approved | DAVID STEPANYAN |
| Smoke Detectors | 2/11/2021 | Approved | DAVID STEPANYAN |
| Final | 3/3/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Final | 3/3/2021 | Approved | DAVID STEPANYAN |
| Final | 10/4/2021 | OK to Issue CofO | DAVID STEPANYAN |