8398-8400 N JASON AVE 91304

Certificate Information: 8398-8400 N JASON AVE 91304

Application / Permit
20014-20000-00542
Plan Check / Job No.
B20VN02109
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 18' 2" X 27' 5" ACCESSORY DWELLING UNIT TO (E) SINGLE FAMILY DWELLING. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 2/24/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2020 APPLICANT
Assigned to Plan Check Engineer 2/7/2020 ANGELICA DAVE
Corrections Issued 2/7/2020 ANGELICA DAVE
Plan Check Approved 2/24/2020 GURUNATH NESARAJAH
Issued 2/24/2020 LADBS
CofO in Progress 10/4/2021 DAVID STEPANYAN
CofO in Progress 10/4/2021 DAVID STEPANYAN
Permit Finaled 10/7/2021 JOHN JANSON
CofO Issued 10/7/2021 JOHN JANSON
Permit Finaled 10/7/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/7/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 2/7/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 2/7/2020 MARKOS PEREZ-BRAN
ZA Case Cleared 2/7/2020 STEVEN WECHSLER
Low Impact Development Cleared 2/21/2020 MARTIN FRAGOSO
Grading Pre-Inspection Cleared 2/24/2020 ANGELICA MARTINEZ
Roof/Waste drainage to street Cleared 2/24/2020 GABRIEL ROBLES

Contact Information

Contractor R S Carpentry Design & Remodeling Inc; Lic. No.: 1023757-B 5737 KANEN RD STE 196      AGOURA HILLS, CA 91301
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/23/2020 Corrections Issued DAVID STEPANYAN
Footing/Foundation/Slab 3/27/2020 Not Ready for Inspection DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 4/1/2020 Not Ready for Inspection DAVID STEPANYAN
Footing/Foundation/Slab 4/13/2020 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 4/16/2020 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 4/28/2020 Corrections Issued DAVID STEPANYAN
Green Building Rough 4/28/2020 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 4/28/2020 Corrections Issued DAVID STEPANYAN
BUILDING-Rough-Frame 5/1/2020 Partial Approval DAVID STEPANYAN
Green Building Rough 5/1/2020 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 5/1/2020 Partial Approval DAVID STEPANYAN
Insulation 5/5/2020 Partial Approval DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 5/7/2020 Corrections Issued DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 5/11/2020 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 7/30/2020 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 7/30/2020 Approved DAVID STEPANYAN
Green Building Rough 7/30/2020 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 7/30/2020 Approved DAVID STEPANYAN
Sewer 7/30/2020 Approved DAVID STEPANYAN
Underground Mechanical 7/30/2020 Partial Approval DAVID STEPANYAN
Deputy Wood Construction 7/31/2020 Approved DAVID STEPANYAN
HVAC-Rough 8/13/2020 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 10/5/2020 Approved DAVID STEPANYAN
Green Building Rough 10/5/2020 Approved DAVID STEPANYAN
HVAC-Rough 10/5/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 10/5/2020 Partial Approval DAVID STEPANYAN
Shower Pan 10/5/2020 Approved DAVID STEPANYAN
Insulation 10/13/2020 Approved DAVID STEPANYAN
Drywall Nailing 10/27/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 10/27/2020 Approved DAVID STEPANYAN
Final 2/11/2021 Corrections Issued DAVID STEPANYAN
Green Building Final 2/11/2021 Not Ready for Inspection DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 2/11/2021 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 2/11/2021 Approved DAVID STEPANYAN
Final 3/3/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Final 3/3/2021 Approved DAVID STEPANYAN
Final 10/4/2021 OK to Issue CofO DAVID STEPANYAN