6430 W DREXEL AVE 90048
Certificate Information: 6430 W DREXEL AVE 90048
- Application / Permit
- 20014-20000-00532
- Plan Check / Job No.
- B20VN02079
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- IRREGULAR ADDITION (94.5 sf) TO (E) CARPORT
- Permit Issued
- Issued on 12/10/2020
- Issuing Office
- Current Status
- CofO Issued on 9/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | SEAN SHAHMIRI |
| Corrections Issued | 2/19/2020 | SEAN SHAHMIRI |
| Plan Check Approved | 8/24/2020 | SEAN SHAHMIRI |
| Issued | 12/10/2020 | APPLICANT |
| CofO in Progress | 8/19/2022 | EVAN COOPER |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
| CofO Issued | 9/9/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/19/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 2/19/2020 | JEANIE LAM |
| Construction near power lines | Cleared | 4/30/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/30/2020 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2020 | PAMELA TENEZA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/5/2021 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 5/5/2021 | Approved | EVAN COOPER |
| METHANE-Subgrade | 5/5/2021 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 5/14/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 7/28/2021 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/31/2021 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 8/31/2021 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2021 | Partial Approval | EVAN COOPER |
| Green Building Rough | 8/31/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 8/31/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 10/13/2021 | Conditional Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 12/23/2021 | Approved | EVAN COOPER |
| Green Building Rough | 12/23/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 12/23/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 8/10/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 8/18/2022 | Approved | EVAN COOPER |
| Final | 8/18/2022 | OK to Issue CofO | EVAN COOPER |
| Green Building Final | 8/18/2022 | Approved | EVAN COOPER |
| HVAC-Final | 8/18/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 8/18/2022 | Approved | EVAN COOPER |
| Smoke Detectors | 8/18/2022 | Approved | EVAN COOPER |