9566 N LAUREL CANYON BLVD 91331

Certificate Information: 9566 N LAUREL CANYON BLVD 91331

Application / Permit
20014-20000-00530
Plan Check / Job No.
B20VN02074
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION OF (N) IRREGULAR SHAPED 37' X 35'ACCESSORY DWELLING UNIT TO (E) 23' X 18' DETACHED GARAGE ALL WORK PER WFPP
Permit Issued
Issued on 8/18/2020
Issuing Office
Current Status
CofO Issued on 7/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/6/2020 APPLICANT
Green Plans Picked Up 3/11/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 3/19/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 4/1/2020 OMID HEDAYAT
Building Plans Picked Up 4/10/2020 APPLICANT
Plan Check Approved 8/18/2020 SEWADA ZADOORAN MILAGARDI
Issued 8/18/2020 APPLICANT
CofO in Progress 7/14/2023 MICHEL ABAJAN
Permit Finaled 7/18/2023 MICHAEL SMITH
CofO Issued 7/18/2023 MICHAEL SMITH
Permit Finaled 7/18/2023 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 4/8/2020 RIDWAN HARDY
Address approval Cleared 5/14/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 5/15/2020 GUILLERMO PETRA
Sewer availability Cleared 5/15/2020 GUILLERMO PETRA
Clean Up Green Up Cleared 5/19/2020 MIGUEL GAMBOA
Green Code Cleared 5/19/2020 MICHAEL AYERS
Hydrant and Access approval Cleared 5/22/2020 MATTHEW CRAIG
Low Impact Development Cleared 7/14/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/20/2020 GUILLERMO PETRA

Contact Information

Contractor Pampa Investment Inc; Lic. No.: 832632-B 984 BROADWAY #302      CHULA VISTA, CA 91911

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/21/2020 Partial Approval MICHEL ABAJAN
Underground Mechanical 8/21/2020 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 8/28/2020 Approved JENNIFER RABUCHIN
Deputy Drilled-In Anchors 9/1/2020 No Access for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 9/24/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 9/24/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/24/2020 Partial Approval MICHEL ABAJAN
Green Building Rough 9/24/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 9/24/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 10/2/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/2/2020 Approved JENNIFER RABUCHIN
Green Building Rough 10/2/2020 Approved JENNIFER RABUCHIN
HVAC-Rough 10/2/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 10/2/2020 Approved JENNIFER RABUCHIN
HVAC-Rough 10/15/2020 Approved MICHEL ABAJAN
Shower Pan 10/15/2020 Approved MICHEL ABAJAN
Insulation 10/22/2020 Approved MICHEL ABAJAN
Drywall Nailing 11/2/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/5/2021 Approved MICHEL ABAJAN
Final 1/5/2021 Corrections Issued MICHEL ABAJAN
Green Building Final 1/5/2021 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 1/5/2021 Approved MICHEL ABAJAN
PLUMBING-Final 1/5/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/5/2021 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 1/5/2021 Approved MICHEL ABAJAN
Final 1/27/2021 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 1/27/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/27/2021 SGSOV Approved MICHEL ABAJAN
Final 2/10/2023 Corrections Issued MICHEL ABAJAN
Final 2/13/2023 Not Ready for Inspection MICHEL ABAJAN
Service/Power Release 2/13/2023 No Access for Inspection MICHEL ABAJAN
Final 7/14/2023 OK to Issue CofO MICHEL ABAJAN