9566 N LAUREL CANYON BLVD 91331
Certificate Information: 9566 N LAUREL CANYON BLVD 91331
- Application / Permit
- 20014-20000-00530
- Plan Check / Job No.
- B20VN02074
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF (N) IRREGULAR SHAPED 37' X 35'ACCESSORY DWELLING UNIT TO (E) 23' X 18' DETACHED GARAGE ALL WORK PER WFPP
- Permit Issued
- Issued on 8/18/2020
- Issuing Office
- Current Status
- CofO Issued on 7/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2020 | APPLICANT |
| Green Plans Picked Up | 3/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 3/19/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 4/1/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 4/10/2020 | APPLICANT |
| Plan Check Approved | 8/18/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 8/18/2020 | APPLICANT |
| CofO in Progress | 7/14/2023 | MICHEL ABAJAN |
| Permit Finaled | 7/18/2023 | MICHAEL SMITH |
| CofO Issued | 7/18/2023 | MICHAEL SMITH |
| Permit Finaled | 7/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/8/2020 | RIDWAN HARDY |
| Address approval | Cleared | 5/14/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 5/15/2020 | GUILLERMO PETRA |
| Clean Up Green Up | Cleared | 5/19/2020 | MIGUEL GAMBOA |
| Green Code | Cleared | 5/19/2020 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 5/22/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 7/14/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/20/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | 984 BROADWAY #302 CHULA VISTA, CA 91911 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/21/2020 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 8/21/2020 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 8/28/2020 | Approved | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 9/1/2020 | No Access for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/24/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/24/2020 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2020 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 9/24/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/24/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/2/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/2/2020 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/2/2020 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/2/2020 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/2/2020 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/15/2020 | Approved | MICHEL ABAJAN |
| Shower Pan | 10/15/2020 | Approved | MICHEL ABAJAN |
| Insulation | 10/22/2020 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 11/2/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/5/2021 | Approved | MICHEL ABAJAN |
| Final | 1/5/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 1/5/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 1/5/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 1/5/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/5/2021 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 1/5/2021 | Approved | MICHEL ABAJAN |
| Final | 1/27/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 1/27/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/27/2021 | SGSOV Approved | MICHEL ABAJAN |
| Final | 2/10/2023 | Corrections Issued | MICHEL ABAJAN |
| Final | 2/13/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Service/Power Release | 2/13/2023 | No Access for Inspection | MICHEL ABAJAN |
| Final | 7/14/2023 | OK to Issue CofO | MICHEL ABAJAN |