14192 W AZTEC ST 91342
Certificate Information: 14192 W AZTEC ST 91342
- Application / Permit
- 20014-20000-00520
- Plan Check / Job No.
- B20VN02043
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2ND FLOOR ADDITION TO & CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNI ( 27'-0"X22'-0") “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 1/27/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 3/18/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 3/24/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 7/15/2020 | APPLICANT |
| Green Plans Picked Up | 7/15/2020 | APPLICANT |
| Applicant returned to address corrections | 8/31/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 1/27/2023 | MOHAMMAD ESMAILI |
| Issued | 1/27/2023 | APPLICANT |
| CofO in Progress | 4/15/2024 | KEVIN BERBERYAN |
| CofO Issued | 4/18/2024 | RUBEN SALAS |
| Permit Finaled | 4/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/8/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 7/28/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 2/7/2022 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 2/10/2022 | CARLOS AGUILERA |
| Green Code | Cleared | 4/6/2022 | AARON COSTA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Avila,, Albert Guerrero; Lic. No.: C41726 | 10034 GLADE AVNENUE CHATSWORTH, CA 91311 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/4/2023 | Partial Inspection | ARAM AVEDISIAN |
| Underground Mechanical | 6/1/2023 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 6/5/2023 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 6/5/2023 | Partial Approval | MICHEL ABAJAN |
| Pre-Inspection | 6/7/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 6/9/2023 | Partial Approval | MICHEL ABAJAN |
| Deputy Wood Construction | 6/14/2023 | Conditional Approval | ROBERT GOLD |
| Underground Mechanical | 6/14/2023 | Corrections Issued | THOMAS FINNILA |
| Sewer | 6/26/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 6/29/2023 | Approved | ARAM AVEDISIAN |
| Deputy Wood Construction | 7/6/2023 | Conditional Approval | ROBERT GOLD |
| PLUMBING-Rough | 7/10/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 7/17/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/18/2023 | Corrections Issued | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Partial Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 7/25/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 7/25/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/25/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/26/2023 | Partial Approval | WILLIAM WREN |
| Interior/Exterior Lathing | 7/31/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/3/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 8/3/2023 | Approved | MICHEL ABAJAN |
| Insulation | 8/7/2023 | Corrections Issued | THOMAS FINNILA |
| Insulation | 8/8/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 8/11/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 9/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 9/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 9/26/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 9/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 9/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 9/26/2023 | Approved | JENNIFER RABUCHIN |
| Final | 10/5/2023 | Corrections Issued | KEVIN BERBERYAN |
| Final | 4/12/2024 | OK to Issue CofO | KEVIN BERBERYAN |