18953 W WYANDOTTE ST 91335

Certificate Information: 18953 W WYANDOTTE ST 91335

Application / Permit
20014-20000-00502
Plan Check / Job No.
B20VN01981
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE 5'-10" X 32' ATTACHED PATIO COVER AND PROPOSED 25'-6" X 32'-1" IRREGULAR SHAPED ADDITION FOR (N) BEDROOM, WIC, BATHROOM AND FAMILY ROOM. REMODEL BEDROOM, BATHROOM, AND KITCHEN. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/19/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/16/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/6/2020 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 RAPHAEL ROSAS
Corrections Issued 2/6/2020 RAPHAEL ROSAS
Plan Check Approved 2/19/2020 HAYATO TSUCHIYA
Issued 2/19/2020 LADBS
CofO in Progress 5/29/2020 MICHAEL SMITH
Permit Finaled 6/16/2020 DONALD SUNSERI
CofO Issued 6/16/2020 DONALD SUNSERI
Permit Finaled 6/16/2020 DONALD SUNSERI

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/6/2020 JOHN LIN
Sewer availability Cleared 2/6/2020 JOHN LIN
Low Impact Development Cleared 2/18/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 2/19/2020 LEE GUILBEAUX

Contact Information

Contractor X S Construction Corporation; Lic. No.: 996597-B 5632 VAN NUYS BLVD #4      VAN NUYS, CA 91401
Engineer Vahdat,, Siamak; Lic. No.: C65255 4 CROSS CREEK      IRVINE, CA 92604

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/21/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 3/31/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Approved VINCENT HANLEY
Green Building Rough 3/31/2020 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 3/31/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/7/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 4/7/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/7/2020 Approved VINCENT HANLEY
Green Building Rough 4/7/2020 Approved VINCENT HANLEY
HVAC-Rough 4/7/2020 Approved VINCENT HANLEY
PLUMBING-Rough 4/7/2020 Approved VINCENT HANLEY
Shower Pan 4/7/2020 Approved VINCENT HANLEY
Insulation 4/10/2020 Approved VINCENT HANLEY
Drywall Nailing 4/16/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/28/2020 Approved VINCENT HANLEY
Final 5/14/2020 Corrections Issued VINCENT HANLEY
Green Building Final 5/14/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/14/2020 SGSOV Approved VINCENT HANLEY
Smoke Detectors 5/14/2020 Approved VINCENT HANLEY
ELECTRICAL-Final 5/18/2020 Approved VINCENT HANLEY
Final 5/18/2020 Corrections Issued VINCENT HANLEY
HVAC-Final 5/18/2020 Approved VINCENT HANLEY
PLUMBING-Final 5/18/2020 Approved VINCENT HANLEY
Service/Power Release 5/18/2020 Approved VINCENT HANLEY
Final 5/28/2020 OK to Issue CofO VINCENT HANLEY