964 S 4TH AVE 90019

Certificate Information: 964 S 4TH AVE 90019

Application / Permit
20014-20000-00486
Plan Check / Job No.
B20VN01913
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRREGULAR SHAPE (33'-6" x 58'-6") ADDITION TO THE REAR OF (E) SINGLE FAMILY DWELLING AND REMODEL (E) KITCHEN.
Permit Issued
Issued on 10/27/2020
Issuing Office
Current Status
CofO Issued on 10/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2020 APPLICANT
Green Plans Picked Up 3/6/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 SEAN SHAHMIRI
Corrections Issued 3/19/2020 SEAN SHAHMIRI
Quality Review Completed 3/19/2020 STEVEN KIM
Building Plans Picked Up 3/19/2020 APPLICANT
Applicant returned to address corrections 9/17/2020 SEAN SHAHMIRI
Applicant returned to address corrections 10/14/2020 SEAN SHAHMIRI
Plan Check Approved 10/14/2020 SEAN SHAHMIRI
Issued 10/27/2020 APPLICANT
CofO in Progress 10/8/2021 CHRIS CHRISTENSEN
Permit Finaled 10/22/2021 DEROLD HAUFF
CofO Issued 10/22/2021 DEROLD HAUFF
Permit Finaled 10/22/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/3/2020 RENZ SORIANO
Sewer availability Cleared 8/3/2020 RENZ SORIANO
Low Impact Development Cleared 8/18/2020 ROBIN YAMADA
Green Code Cleared 8/21/2020 DAVID MATSON
HPOZ Cleared 8/25/2020 AMANDA KAINER
ZI Cleared 8/25/2020 AMANDA KAINER
Roof/Waste drainage to street Cleared 8/26/2020 RENZ SORIANO

Contact Information

Contractor Savs Enterprises; Lic. No.: 814956-B 4500 SUNNYCREST DRIVE      LOS ANGELES, CA 90065
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/5/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 11/20/2020 Partial Approval JOSEPH MCGARRY
Gas Test 11/20/2020 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 11/20/2020 Partial Approval JOSEPH MCGARRY
HVAC-Rough 1/21/2021 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 1/21/2021 Partial Approval CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 1/21/2021 Partial Approval CHRIS CHRISTENSEN
Shower Pan 1/21/2021 Approved CHRIS CHRISTENSEN
Wood Frame 1/21/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/27/2021 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 1/27/2021 Partial Approval JOSEPH MCGARRY
Green Building Rough 1/27/2021 Approved JOSEPH MCGARRY
HVAC-Rough 1/27/2021 Approved JOSEPH MCGARRY
Insulation 1/27/2021 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 1/27/2021 Approved JOSEPH MCGARRY
PLUMBING-Rough 1/27/2021 Approved JOSEPH MCGARRY
Drywall Nailing 2/1/2021 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 2/1/2021 Partial Approval STUART CHAPMAN
Insulation 2/1/2021 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 2/3/2021 Approved CHRIS CHRISTENSEN
Insulation 2/3/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 2/4/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 5/19/2021 Approved CHRIS CHRISTENSEN
Final 5/19/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 5/19/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 5/19/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 5/19/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/19/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 5/19/2021 Approved CHRIS CHRISTENSEN
Final 10/7/2021 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 10/7/2021 Approved CHRIS CHRISTENSEN