4329 N TALOFA AVE 91602

Certificate Information: 4329 N TALOFA AVE 91602

Application / Permit
20014-20000-00473
Plan Check / Job No.
B20VN01831
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD NEW (5.5'X5.25') ELEVATOR SHAFT TO (E) SFD W/ATT. GARAGE, PER DIR-2019-5132-R40..
Permit Issued
Issued on 7/27/2020
Issuing Office
Current Status
Issued on 7/27/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/4/2020 APPLICANT
Green Plans Picked Up 2/19/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 ABDUL CHEGENI
Corrections Issued 2/24/2020 ABDUL CHEGENI
Quality Review Completed 2/24/2020 STEVEN KIM
Building Plans Picked Up 2/26/2020 APPLICANT
Plan Check Approved 5/6/2020 SELLA BENYAMIN
Issued 7/27/2020 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/4/2020 GABRIEL ROBLES
Green Code Cleared 3/4/2020 AARON COSTA
Roof/Waste drainage to street Cleared 3/4/2020 GABRIEL ROBLES
ZA Case Cleared 3/18/2020 PABLO ESTRADA

Contact Information

Contractor Mulick Construction And Design Inc; Lic. No.: 372231-B 1476 DORSET AVENUE      THOUSAND OAKS, CA 91360
Engineer Andrejic,, Milos M; Lic. No.: C67443 3601 BEVERLY RIDGE DR      SHERMAN OAKS, CA 91423

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/29/2020 Corrections Issued THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 8/5/2020 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 8/5/2020 Conditional Approval THOMAS FINNILA
Wood Frame 8/26/2020 Corrections Issued THOMAS FINNILA
Deputy Drilled-In Anchors 8/27/2020 Conditional Approval THOMAS FINNILA
Deputy Wood Construction 8/27/2020 Conditional Approval THOMAS FINNILA
Wood Frame 9/2/2020 Approved THOMAS FINNILA
Drywall Nailing 9/8/2020 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 9/8/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 9/8/2020 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 9/14/2020 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 10/1/2020 Approved THOMAS FINNILA
BUILDING-Rough-Frame 10/21/2020 Approved THOMAS FINNILA
Drywall Nailing 10/21/2020 Approved THOMAS FINNILA
Footing/Foundation/Slab 10/21/2020 Approved THOMAS FINNILA
Green Building Final 10/21/2020 Not Ready for Inspection THOMAS FINNILA
Final 12/15/2020 No Access for Inspection THOMAS FINNILA
Green Building Final 12/15/2020 No Access for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/15/2020 SGSOV Approved THOMAS FINNILA
Smoke Detectors 12/15/2020 Corrections Issued THOMAS FINNILA
Final 12/24/2020 Partial Approval THOMAS FINNILA
Green Building Final 12/24/2020 Approved THOMAS FINNILA
Smoke Detectors 12/24/2020 Approved THOMAS FINNILA