6513 N HAZELTINE AVE 91401

Certificate Information: 6513 N HAZELTINE AVE 91401

Application / Permit
20014-20000-00451
Plan Check / Job No.
B20VN01735
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 18' X 13' TO & CONVERT (E) 18' X 18' DETACHED GARAGE TO ACCESSORY DWELLING UNIT , ALL WORK PER WFPP; "COMPLY WITH DEPARTMENT ORDER effective date 01/16/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 3/11/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/22/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2020 APPLICANT
Assigned to Plan Check Engineer 2/4/2020 RARES BODEA
Corrections Issued 2/4/2020 RARES BODEA
Building Plans Picked Up 2/10/2020 APPLICANT
Plan Check Approved 3/10/2020 RARES BODEA
Issued 3/11/2020 LADBS
CofO in Progress 10/19/2020 BRYAN MEYER
CofO in Progress 10/20/2020 BRYAN MEYER
Permit Finaled 10/22/2020 DAVID JAMES
CofO Issued 10/22/2020 DAVID JAMES
Permit Finaled 10/22/2020 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 2/12/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 2/12/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 2/12/2020 GUILLERMO PETRA
"Q" conditions Cleared 2/25/2020 DANG NGUYEN
Sewer availability Cleared 2/25/2020 JOHN TRIANTAFYLLOS
ZA Case Cleared 2/25/2020 DANG NGUYEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/16/2020 Partial Inspection BRYAN MEYER
BUILDING-Rough-Frame 5/13/2020 Not Ready for Inspection BRYAN MEYER
ELECTRICAL-Rough 5/13/2020 Not Ready for Inspection BRYAN MEYER
Footing/Foundation/Slab 5/13/2020 Not Ready for Inspection BRYAN MEYER
Green Building Rough 5/13/2020 Not Ready for Inspection BRYAN MEYER
BUILDING-Rough-Frame 6/2/2020 Not Ready for Inspection BRYAN MEYER
ELECTRICAL-Rough 6/2/2020 Not Ready for Inspection BRYAN MEYER
Footing/Foundation/Slab 6/2/2020 Not Ready for Inspection BRYAN MEYER
PLUMBING-Rough 6/2/2020 Not Ready for Inspection BRYAN MEYER
Footing/Foundation/Slab 7/21/2020 Corrections Issued BRYAN MEYER
Footing/Foundation/Slab 7/29/2020 Approved BRYAN MEYER
Sewer 7/29/2020 Partial Approval BRYAN MEYER
BUILDING-Rough-Frame 8/6/2020 Partial Inspection BRYAN MEYER
Green Building Rough 8/6/2020 Not Ready for Inspection BRYAN MEYER
PLUMBING-Rough 8/6/2020 Partial Inspection BRYAN MEYER
BUILDING-Rough-Frame 8/14/2020 Approved BRYAN MEYER
ELECTRICAL-Rough 8/14/2020 Partial Inspection BRYAN MEYER
Gas Test 8/14/2020 Partial Approval BRYAN MEYER
Green Building Rough 8/14/2020 Approved BRYAN MEYER
HVAC-Rough 8/14/2020 Not Ready for Inspection BRYAN MEYER
PLUMBING-Rough 8/14/2020 Partial Approval BRYAN MEYER
HVAC-Rough 8/20/2020 Approved BRYAN MEYER
Insulation 8/20/2020 Approved BRYAN MEYER
Sewer 8/27/2020 Approved BRYAN MEYER
Drywall Nailing 8/28/2020 Approved BRYAN MEYER
Interior/Exterior Lathing 9/2/2020 Corrections Issued BRYAN MEYER
Interior/Exterior Lathing 9/8/2020 Not Ready for Inspection BRYAN MEYER
Interior/Exterior Lathing 9/9/2020 Approved BRYAN MEYER
Interior/Exterior Lathing 9/15/2020 Approved BRYAN MEYER
ELECTRICAL-Final 10/5/2020 Approved BRYAN MEYER
Final 10/5/2020 Partial Inspection BRYAN MEYER
Green Building Final 10/5/2020 Approved BRYAN MEYER
HVAC-Final 10/5/2020 Approved BRYAN MEYER
PLUMBING-Final 10/5/2020 Partial Approval BRYAN MEYER
SGSOV-Seismic Gas S/O Valve 10/5/2020 SGSOV Approved BRYAN MEYER
Smoke Detectors 10/5/2020 Partial Approval BRYAN MEYER
Final 10/19/2020 OK to Issue CofO BRYAN MEYER
Smoke Detectors 10/19/2020 Approved BRYAN MEYER