22559 W CLARENDON ST 91367

Certificate Information: 22559 W CLARENDON ST 91367

Application / Permit
20014-20000-00441
Plan Check / Job No.
B20VN01716
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 14'-0" X 10'-9" ADDITION TO REAR OF (E) SINGLE FAMILY DWELLING. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 2/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2020 APPLICANT
Assigned to Plan Check Engineer 2/3/2020 SARKIS HARABEDIAN
Corrections Issued 2/3/2020 SARKIS HARABEDIAN
Plan Check Approved 2/4/2020 LUIS RINCON
Issued 2/13/2020 LADBS
CofO in Progress 6/25/2020 TROY SANDERS
CofO Issued 7/2/2020 JOHN JANSON
Permit Finaled 7/2/2020 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/4/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 2/4/2020 MANUEL TEJADA
Roof/Waste drainage to street Cleared 2/4/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/4/2020 JOHN TRIANTAFYLLOS

Contact Information

Engineer Sabzehzar,, Habib; Lic. No.: C50442 8180 N PRICE AVE      FRESNO, CA 93720

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/25/2020 Partial Approval JOHN KIDWELL
PLUMBING-Rough 2/25/2020 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 2/28/2020 Partial Approval JOHN KIDWELL
PLUMBING-Rough 3/3/2020 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 3/9/2020 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Partial Approval JOHN KIDWELL
Wood Frame 3/31/2020 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 4/8/2020 Partial Approval JOHN KIDWELL
Rough-Elec/Plmb/HVAC 4/8/2020 Partial Approval JOHN KIDWELL
Shower Pan 4/8/2020 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 4/10/2020 Approved JOHN KIDWELL
Green Building Rough 4/10/2020 Approved JOHN KIDWELL
HVAC-Rough 4/10/2020 Approved JOHN KIDWELL
Insulation 4/10/2020 Approved JOHN KIDWELL
Shower Pan 4/10/2020 Approved JOHN KIDWELL
Drywall Nailing 4/13/2020 Approved JOHN KIDWELL
Green Building Rough 4/13/2020 Approved JOHN KIDWELL
Interior/Exterior Lathing 4/30/2020 Partial Approval JOHN KIDWELL
ELECTRICAL-Final 6/22/2020 Approved TROY SANDERS
Final 6/22/2020 Corrections Issued TROY SANDERS
Footing/Foundation/Slab 6/22/2020 Approved TROY SANDERS
Green Building Final 6/22/2020 Approved TROY SANDERS
HVAC-Final 6/22/2020 Approved TROY SANDERS
PLUMBING-Final 6/22/2020 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 6/22/2020 SGSOV Approved TROY SANDERS
Smoke Detectors 6/22/2020 Approved TROY SANDERS
Final 6/25/2020 OK to Issue CofO TROY SANDERS