10521 W ADDISON ST 91601
Certificate Information: 10521 W ADDISON ST 91601
- Application / Permit
- 20014-20000-00430
- Plan Check / Job No.
- B20VN01671
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE ONE STORY ADDITION AND MAJOR REMODEL TO (E) SFD _ PER ENGINEERED PLANS.
- Permit Issued
- Issued on 10/17/2020
- Issuing Office
- Current Status
- CofO Issued on 9/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | DAWN MC NULTY |
| Corrections Issued | 3/13/2020 | DAWN MC NULTY |
| Quality Review Completed | 3/18/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/19/2020 | APPLICANT |
| Green Plans Picked Up | 3/19/2020 | APPLICANT |
| Applicant returned to address corrections | 6/10/2020 | DAWN MC NULTY |
| Plan Check Approved | 6/23/2020 | DAWN MC NULTY |
| Issued | 10/17/2020 | APPLICANT |
| CofO in Progress | 6/2/2021 | JOHN HAYES |
| CofO Issued | 9/11/2021 | MICHAEL SMITH |
| Permit Finaled | 9/11/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| CPC | Cleared | 3/24/2020 | MIGUEL GAMBOA |
| Permit | Cleared | 3/25/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/25/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 5/15/2020 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2020 | ADRIAN CASTRO |
| Green Code | Cleared | 5/21/2020 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 5/27/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C89103 | GLENDALE, CA 91205 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/19/2020 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2020 | Partial Approval | DANIEL DREW |
| PLUMBING-Rough | 12/8/2020 | Partial Approval | DANIEL DREW |
| BUILDING-Rough-Frame | 12/9/2020 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2020 | Partial Approval | DANIEL DREW |
| Green Building Rough | 12/9/2020 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Rough | 12/9/2020 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2021 | Not Ready for Inspection | DANIEL DREW |
| Deputy Wood Construction | 1/15/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 1/25/2021 | Approved | DANIEL DREW |
| HVAC-Rough | 1/26/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 1/26/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 1/29/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 1/29/2021 | Approved | DANIEL DREW |
| Green Building Rough | 1/29/2021 | Approved | DANIEL DREW |
| Insulation | 2/3/2021 | Approved | DANIEL DREW |
| Drywall Nailing | 2/8/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 2/19/2021 | Approved | DANIEL DREW |
| Shower Pan | 2/19/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 5/7/2021 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 5/7/2021 | Approved | MISAEL ESPARZA |
| HVAC-Final | 5/10/2021 | Approved | DAVID MATSON |
| HVAC-Rough | 5/10/2021 | Not Ready for Inspection | DAVID MATSON |
| Final | 5/18/2021 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 5/18/2021 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/18/2021 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 5/18/2021 | Approved | ARAM AVEDISIAN |
| Smoke Detectors | 5/18/2021 | Approved | ARAM AVEDISIAN |
| Final | 6/1/2021 | OK to Issue CofO | JOHN HAYES |