1535 S GENESEE AVE 90019
Certificate Information: 1535 S GENESEE AVE 90019
- Application / Permit
- 20014-20000-00425
- Plan Check / Job No.
- B20VN01659
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 23' X 24'-6" ADDITION TO (E) SINGLE FAMILY DWELLING TO EXPAND KITCHEN AND FAMILY ROOM. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 4/13/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/8/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2020 | SERGIO MUNIZ |
| Corrections Issued | 1/31/2020 | SERGIO MUNIZ |
| Applicant returned to address corrections | 2/10/2020 | MOHAMMAD ESMAILI |
| Plan Check Approved | 3/27/2020 | GURUNATH NESARAJAH |
| Issued | 4/13/2020 | LADBS |
| CofO in Progress | 9/24/2020 | DAVID CHAN |
| Permit Finaled | 10/8/2020 | DEROLD HAUFF |
| CofO Issued | 10/8/2020 | DEROLD HAUFF |
| Permit Finaled | 10/8/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 1/31/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/21/2020 | Approved | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2020 | Conditional Approval | DAVID CHAN |
| Insulation | 6/4/2020 | Partial Approval | THOMAS LOGRASSO |
| Wood Frame | 6/17/2020 | Partial Approval | DAVID CHAN |
| ELECTRICAL-Rough | 6/23/2020 | Approved | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2020 | Not Ready for Inspection | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 7/10/2020 | Partial Approval | DAVID CHAN |
| HVAC-Rough | 7/10/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 7/10/2020 | Approved | DAVID CHAN |
| Insulation | 7/14/2020 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 7/17/2020 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 7/17/2020 | Partial Approval | ROBERT VORHIS |
| Drywall Nailing | 7/21/2020 | Approved | DAVID CHAN |
| Wood Frame | 7/21/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 9/11/2020 | Approved | DAVID CHAN |
| Final | 9/11/2020 | Conditional Approval | DAVID CHAN |
| Footing/Foundation/Slab | 9/11/2020 | Approved | DAVID CHAN |
| Green Building Final | 9/11/2020 | Approved | DAVID CHAN |
| Green Building Rough | 9/11/2020 | Approved | DAVID CHAN |
| METHANE-Barrier | 9/11/2020 | Approved | DAVID CHAN |
| METHANE-Final | 9/11/2020 | Approved | DAVID CHAN |
| METHANE-Rough | 9/11/2020 | Approved | DAVID CHAN |
| METHANE-Subgrade | 9/11/2020 | Approved | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 9/11/2020 | SGSOV Approved | DAVID CHAN |
| Smoke Detectors | 9/11/2020 | Approved | DAVID CHAN |
| Final | 9/22/2020 | OK to Issue CofO | DAVID CHAN |
| PLUMBING-Final | 9/22/2020 | Approved | DAVID CHAN |