19606 W VICTORY BLVD 91335

Certificate Information: 19606 W VICTORY BLVD 91335

Application / Permit
20014-20000-00424
Plan Check / Job No.
B20VN01654
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
25'-6" X 44'-5" ADDITION TO (E) DETACHED 1-STORY GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER STATE ORDINANCE 186,481.
Permit Issued
Issued on 6/22/2021
Issuing Office
Current Status
CofO Issued on 7/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2020 APPLICANT
Green Plans Picked Up 3/6/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 SERGIO MUNIZ
Corrections Issued 3/16/2020 SERGIO MUNIZ
Quality Review Completed 4/10/2020 OMID HEDAYAT
Applicant returned to address corrections 1/10/2021 SERGIO MUNIZ
Plan Check Approved 3/5/2021 SERGIO MUNIZ
Building Plans Picked Up 4/12/2021 APPLICANT
Issued 6/22/2021 APPLICANT
CofO in Progress 7/13/2022 STEVEN BACK
CofO Issued 7/22/2022 JOHN JANSON
Permit Finaled 7/22/2022 JOHN JANSON

Permit Application Clearance Information

Green Code Cleared 4/14/2020 AARON COSTA
Address approval Cleared 7/14/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/29/2020 LEE GUILBEAUX
Sewer availability Cleared 7/29/2020 LEE GUILBEAUX
Low Impact Development Cleared 12/18/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 12/28/2020 ADRIAN CASTRO

Contact Information

Contractor Arpa Design - Build Company Inc; Lic. No.: 885655-B 1146 N CENTRAL AVE #538      GLENDALE, CA 91202
Engineer Gosen,, James W; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 10/19/2021 No Access for Inspection STEVEN BACK
Deputy Drilled-In Anchors 12/3/2021 Approved STEVEN BACK
Pre-Inspection 12/3/2021 Partial Inspection STEVEN BACK
PLUMBING-Rough 12/15/2021 Not Ready for Inspection STEVEN BACK
Excavation/Setback/Form/Re-Bar 12/29/2021 Corrections Issued STEVEN BACK
PLUMBING-Rough 12/29/2021 Not Ready for Inspection STEVEN BACK
Excavation/Setback/Form/Re-Bar 1/10/2022 Approved STEVEN BACK
Footing/Foundation/Slab 1/10/2022 Approved STEVEN BACK
PLUMBING-Rough 1/10/2022 Partial Approval STEVEN BACK
Sewer 1/10/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/7/2022 Partial Approval STEVEN BACK
Pre-Inspection 3/7/2022 Partial Inspection STEVEN BACK
Deputy Wood Construction 3/17/2022 Conditional Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Approved STEVEN BACK
Interior/Exterior Lathing 3/18/2022 Partial Approval STEVEN BACK
Rough-Elec/Plmb/HVAC 3/18/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 3/23/2022 Approved STEVEN BACK
Green Building Rough 3/23/2022 Approved STEVEN BACK
Insulation 3/25/2022 Approved MORRIS JACKSON
Drywall Nailing 4/4/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 4/4/2022 Approved MORRIS JACKSON
Shower Pan 4/4/2022 Approved MORRIS JACKSON
Service/Power Release 6/29/2022 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Final 7/6/2022 Approved STEVEN BACK
Final 7/6/2022 Corrections Issued STEVEN BACK
Green Building Final 7/6/2022 Approved STEVEN BACK
HVAC-Final 7/6/2022 Not Ready for Inspection STEVEN BACK
PLUMBING-Final 7/6/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 7/6/2022 SGSOV Not Ready STEVEN BACK
Service/Power Release 7/6/2022 Not Ready for Inspection STEVEN BACK
Smoke Detectors 7/6/2022 Approved STEVEN BACK
Final 7/13/2022 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 7/13/2022 SGSOV Approved STEVEN BACK