4549 N TOBIAS AVE 91403

Certificate Information: 4549 N TOBIAS AVE 91403

Application / Permit
20014-20000-00405
Plan Check / Job No.
B20VN01548
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO REMOVE (E) BUILDING FOOTPRINT EXCEPT FOR 16' OF WALL ON SOUTHWEST SIDE TO CREATE (N) 51'-2" X 40' 1-STORY SINGLE FAMILY DWELLING. SPRINKLER REQUIRED NFPA-13D.
Permit Issued
Issued on 3/5/2021
Issuing Office
Current Status
CofO Issued on 8/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 SERGIO MUNIZ
Corrections Issued 3/11/2020 SERGIO MUNIZ
Quality Review Completed 3/16/2020 OMID HEDAYAT
Building Plans Picked Up 3/20/2020 APPLICANT
Green Plans Picked Up 3/20/2020 APPLICANT
Plan Check Approved 2/11/2021 SERGIO MUNIZ
Issued 3/5/2021 APPLICANT
CofO in Progress 8/3/2022 JACK KARGODORIAN
Permit Finaled 8/13/2022 DEROLD HAUFF
CofO Issued 8/13/2022 DEROLD HAUFF
Permit Finaled 8/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 7/1/2020 LEE GUILBEAUX
ZI Cleared 8/4/2020 SHEILA GERSHON
Eng Process Fee Ord 176,300 Cleared 1/4/2021 LEE GUILBEAUX
Low Impact Development Cleared 1/13/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/13/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/13/2021 LEE GUILBEAUX
Green Code Cleared 2/11/2021 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/24/2021 Approved CHARLES POWELL
Footing/Foundation/Slab 4/13/2021 Partial Approval CHARLES POWELL
PLUMBING-Rough 4/13/2021 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 4/20/2021 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 5/4/2021 Partial Approval CHARLES POWELL
HVAC-Rough 5/24/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 5/28/2021 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 5/28/2021 Approved CHARLES POWELL
PLUMBING-Rough 5/28/2021 Approved CHARLES POWELL
Insulation 6/8/2021 Partial Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 6/8/2021 Partial Approval JESUS RODRIGUEZ
Shower Pan 6/8/2021 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 6/9/2021 Approved CHARLES POWELL
Green Building Rough 6/9/2021 Approved CHARLES POWELL
Interior/Exterior Lathing 6/18/2021 Approved JAVIER RAMOS JR
Drywall Nailing 6/28/2021 Approved JAVIER RAMOS JR
ELECTRICAL-Final 12/14/2021 Corrections Issued MISAEL ESPARZA
HVAC-Final 1/11/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 7/19/2022 Corrections Issued MISAEL ESPARZA
Final 7/19/2022 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 7/19/2022 Approved MISAEL ESPARZA
HVAC-Final 7/19/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 7/19/2022 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 7/19/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 8/3/2022 Approved JACK KARGODORIAN
Final 8/3/2022 OK to Issue CofO JACK KARGODORIAN
HVAC-Final 8/3/2022 Approved JACK KARGODORIAN
PLUMBING-Final 8/3/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 8/3/2022 SGSOV Approved JACK KARGODORIAN