5028 N GREENBUSH AVE 91423

Certificate Information: 5028 N GREENBUSH AVE 91423

Application / Permit
20014-20000-00404
Plan Check / Job No.
B20VN01541
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
56'-7" X 35'-7" IREGULAR SHAPE ADDITION & (N) 9' X 14'-5" PATIO COVER TO (E) 1-STORY SINGLE FAMILY DWELLING. DEMO (E) 31'-8" X 12' PATIO COVER. INTERIOR REMODEL.
Permit Issued
Issued on 9/1/2020
Issuing Office
Metro
Current Status
CofO Issued on 7/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2020 APPLICANT
Green Plans Picked Up 2/14/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 SERGIO MUNIZ
Corrections Issued 2/24/2020 SERGIO MUNIZ
Quality Review Completed 2/26/2020 OMID HEDAYAT
Building Plans Picked Up 3/3/2020 APPLICANT
Applicant returned to address corrections 6/30/2020 SERGIO MUNIZ
Applicant returned to address corrections 7/22/2020 SERGIO MUNIZ
Plan Check Approved 7/24/2020 SERGIO MUNIZ
Issued 9/1/2020 APPLICANT
CofO in Progress 5/16/2022 MISAEL ESPARZA
CofO Issued 7/16/2022 MICHAEL SMITH
Permit Finaled 7/16/2022 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 4/16/2020 AARON COSTA
ZI Cleared 4/27/2020 HERMINIGILDO AGUSTIN
Roof/Waste drainage to street Cleared 6/11/2020 GUILLERMO PETRA
Sewer availability Cleared 6/11/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 6/12/2020 GUILLERMO PETRA
Low Impact Development Cleared 7/22/2020 ROBIN YAMADA

Contact Information

Architect Yotnegparian,, Alain Levon; Lic. No.: C26374 11541 DONA PEPITA PLACE      STUDIO CITY, CA 91604
Contractor Red Stag Construction Company; Lic. No.: 964664-B 9948 SEPULVEDA BLVD #6      MISSION HILLS, CA 91345
Engineer Koh,, William Kim; Lic. No.: S3473 5695 STARWOOD CT      WESTLAKE VILLAGE, CA 91362

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/24/2020 Not Ready for Inspection CHARLES POWELL
Footing/Foundation/Slab 10/2/2020 Corrections Issued ARAM AVEDISIAN
Deputy Drilled-In Anchors 10/6/2020 Approved MISAEL ESPARZA
Footing/Foundation/Slab 10/8/2020 Approved ARAM AVEDISIAN
Deputy Reinf. Concrete 10/9/2020 Conditional Approval DANIEL ORRANTE
BUILDING-Rough-Frame 10/29/2020 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 10/29/2020 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 11/9/2020 Not Ready for Inspection ARAM AVEDISIAN
Deputy Steel/Welding 12/23/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 12/23/2020 Partial Approval CHARLES POWELL
Green Building Rough 12/23/2020 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 1/29/2021 Not Ready for Inspection CHARLES POWELL
HVAC-Rough 1/29/2021 Not Ready for Inspection CHARLES POWELL
PLUMBING-Rough 1/29/2021 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 2/3/2021 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/3/2021 Partial Approval ARAM AVEDISIAN
HVAC-Rough 2/3/2021 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 2/3/2021 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 2/11/2021 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 2/11/2021 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 2/11/2021 Approved ARAM AVEDISIAN
Insulation 2/18/2021 Approved ARAM AVEDISIAN
Drywall Nailing 2/23/2021 Approved JOHN HAYES
Green Building Rough 2/23/2021 Approved JOHN HAYES
Shower Pan 2/23/2021 Not Ready for Inspection JOHN HAYES
Shower Pan 3/23/2021 Corrections Issued CHARLES POWELL
Shower Pan 3/31/2021 Approved JOHN HAYES
Interior/Exterior Lathing 5/3/2021 Approved MORRIS JACKSON
Special/Order Compliance 5/3/2021 Partial Inspection ALIZAH MAYAGOITIA
Deputy Drilled-In Anchors 7/19/2021 Conditional Approval DANIEL ORRANTE
Deputy Drilled-In Anchors 7/20/2021 Approved CHARLES POWELL
Reinforced Concrete Frame 7/22/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 2/25/2022 Approved MISAEL ESPARZA
Final 2/25/2022 Corrections Issued MISAEL ESPARZA
Green Building Final 2/25/2022 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/25/2022 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 2/25/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 4/21/2022 Approved MISAEL ESPARZA
Final 4/21/2022 Corrections Issued MISAEL ESPARZA
Green Building Final 4/21/2022 Approved MISAEL ESPARZA
HVAC-Final 4/21/2022 Approved MISAEL ESPARZA
PLUMBING-Final 4/21/2022 Approved MISAEL ESPARZA
Smoke Detectors 4/21/2022 Approved MISAEL ESPARZA
Final 5/13/2022 OK to Issue CofO MISAEL ESPARZA